首页> 外文期刊>Maritime Journal >WIND JACK-UP CRANE - MAIN BOOM UPGRADE COMPLETED
【24h】

WIND JACK-UP CRANE - MAIN BOOM UPGRADE COMPLETED

机译:风速提升起重机-主臂升级完成

获取原文
获取原文并翻译 | 示例
   

获取外文期刊封面封底 >>

       

摘要

The operation to insert the additional section took 30 days in total. It required the unreeving of all the crane wires before the crane boom could be dropped down to rest on a support structure built from containers. The boom was then cut in two and the new section inserted and secured using flanges. Following the completion of the new boom the wires were re-reeved and a series of load tests conducted before the crane was certified ready for operations. The main operation was the insertion of a 20-metre section into the main boom of the 8oo-tonne crane, allowing it to reach a height of 120 metres. This upgrade now allows it to install and maintain the next generation of wind turbines To secure the order, Damen Shiprepair Amsterdam (DSAm) offered a fast turnaround time without any loss of quality or attention to detail. Not only was the project time highly competitive, the actual order was only received the day before the vessel arrived at the yard.
机译:插入附加部分的操作总共花费了30天。在吊臂下降到由集装箱建造的支撑结构上之前,需要使所有吊线保持整齐。然后将动臂切成两部分,然后插入新部分,并使用法兰固定。新动臂完成后,重新吊装钢丝绳并进行了一系列负载测试,然后再证明起重机可以投入使用。主要操作是在8oo吨起重机的主吊臂中插入20米长的部分,使其达到120米的高度。现在,此升级使它能够安装和维护下一代风力涡轮机。为了确保订单,阿姆斯特丹达门修船厂(DSAm)提供了快速的周转时间,而不会损失质量或关注细节。项目时间不仅竞争激烈,而且仅在船只到达船坞的前一天才收到实际订单。

著录项

  • 来源
    《Maritime Journal》 |2018年第366期|10-10|共1页
  • 作者

  • 作者单位
  • 收录信息
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类
  • 关键词

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号