Earned Value Management (EVM) has been established as a project management technique for project monitoring and control. The traditional EVM performs well in forecasting Cost Performance index and other cost metrics. However, in terms of schedule performance, the accuracy of the forecasted schedule metrics through the traditional EVM approach are always questionable. The schedule performance is not measured in time unit but rather in monetary units or uses cost information, which may cause misleading in the interpretation of the EVM schedule metrics. The schedule performance is not accurately forecasted, resulting in underestimating the estimate at completion (t). Even the renowned Earned Schedule also uses cost as a proxy to determine the earned schedule. This paper presents a new EVM tool, Duration estimate at completion (DEAC-model) developed to accurately forecast the time estimate at completion. DEAC-model uses the actual time spent on each activity, either in progress or upon completion, where the Performance is measured in time units. The benefits of DEAC-model to project management team and researchers are that it can be used: 1) to forecast schedule metrics accurately so that resources can be effectively allocated to complete the remaining activities, 2) as a gauge to assess if the project can be completed within the plan schedule, and 3) to apply time series and simple linear regression model concepts using excel worksheet syntax to forecast duration estimate at completion that is easily applicable.
机译:挣值管理(EVM)已建立为用于项目监视和控制的项目管理技术。传统的EVM在预测成本绩效指数和其他成本指标方面表现良好。但是,就进度表性能而言,通过传统的EVM方法预测的进度表指标的准确性始终令人怀疑。计划绩效不是以时间单位衡量,而是以货币单位或使用成本信息来衡量,这可能会导致对EVM计划指标的解释产生误导。进度表的性能未得到准确的预测,从而导致对完成时间(t)的估计值低估。甚至著名的“收入时间表”也使用成本作为代理来确定收入时间表。本文介绍了一种新的EVM工具,即完成时持续时间估算(DEAC模型),可以准确预测完成时的时间估算。 DEAC模型使用进行中或完成时在每个活动上花费的实际时间,其中以时间单位衡量绩效。 DEAC模型对项目管理团队和研究人员的好处是可以使用它:1)准确预测进度指标,以便可以有效地分配资源来完成剩余的活动,2)作为评估项目是否可以进行的量度在计划进度表中完成; 3)使用Excel工作表语法应用时间序列和简单的线性回归模型概念来预测完成时的持续时间估算,这很容易实现。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号