General Disclaimer Does Not Defeat Differing Site Conditions Claim

机译:一般性免责声明不胜诉不同的现场条件索赔

获取原文
获取原文并翻译 | 示例
       

摘要

Differing site conditions clauses are ubiquitous, and sometimes required, in construction contracts. Typical of these clauses are provisions that call for an equitable adjustment to the contract in the event that conditions at the site are materially different from those indicated in the contract documents, or if the conditions are materially different from what one would normally expect to encounter at the site. In tension with the traditional differing site conditions clauses are disclaimers of responsibility for soils reports and other site information included in the contract documents that are intended to shift responsibility for assessing site conditions from the owner who provides the information to the contractor that is doing the work. The California Court of Appeals held in Condon-Johnson and Associates, Inc. v. Sacramento Municipal Utility District that a general disclaimer of provided soils reports is not enough to overcome a statutory differing site conditions clause.
机译:在建筑合同中,不同的场地条件条款无处不在,有时是必需的。这些条款中的典型规定是:如果现场条件与合同文件中所示的条件大不相同,或者如果条件与正常情况下通常期望遇到的条件大不相同,则要求对合同进行公平的调整。网站。与传统的场地条件不同,条款中免除了对土壤报告和合同文件中包含的其他场地信息的责任,旨在将评估场地条件的责任从提供信息的所有者转移到进行这项工作的承包商。在Condon-Johnson and Associates,Inc.诉萨克拉曼多市政公用事业区一案中,加利福尼亚州上诉法院认为,对提供的土壤报告的一般性否认不足以克服法定的场地条件不同条款。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号