R. (on the application of PPG11 Limited) v Dorset County Council and Viridor Waste Management Limited

机译:R.(根据PPG11 Limited的申请)v Dorset County Council and Viridor Waste Management Limited

获取原文
获取原文并翻译 | 示例
   

获取外文期刊封面封底 >>

       

摘要

Trigon Hill Quarry was an open cast clay quarry. Permissions existed under which clay could be extracted from the site until 2015. In December 1999 Viridor Waste Management Limited (Viridor) applied to Dorset County Council (Dorset) for planning permission to use the quarry as a landfill site for controlled waste. The scheme as presented sought permission to deposit waste for some 20 years commencing in 2002 after which the site would be restored to match the surrounding heathland area. The proposed access road was routed so as to avoid, in the main, land of an ecologically sensitive nature. The net result of the scheme was that the two areas of heathland lying north and south of the clay quarry, each of which was a Site of Nature Conservation Interest (SNCI) would be reunited upon the completion of the filling of the quarry when it would be covered by a new managed heathland area. Incorporated within the application was an Environmental Statement dated December 1998. There was substantial consultation following submission of the application, including two public meetings and the submission of a mass of written material, all of which was before Dorset when its relevant committee met. It also had before it a report from its Director of Environmental Services and the advice of the County Ecologist. In his report the Director considered the adequacy of the Environmental Impact Assessment (EIA) work done by the applicant in the particular area of nature conservation and set out the proposed mitigation measures. The report concluded that provided these measures were adequately secured, it was considered that in this particular case the planning authority could reasonably and rationally conclude that there would not be significant adverse effects on protected species or important areas for nature conservation.
机译:三角山采石场是一个露天粘土采石场。根据许可,可以从该场地开采粘土直到2015年。1999年12月,Viridor废物管理有限公司(Viridor)向多塞特郡议会(Dorset)申请规划许可,以将采石场用作受控废物的填埋场。所提出的计划寻求从2002年开始的20年左右的废物存放许可,此后将对场地进行修复以匹配周围的荒地。拟议的进出道路的路线是为了避开主要是生态敏感的土地。该方案的最终结果是,位于石矿场南北的两个荒地,这两个自然保护区(SNCI)将在石矿场填满后重新统一。被新管理的欧石南丛生地区覆盖。申请书中包含了日期为1998年12月的环境声明。提交申请书后进行了实质性的磋商,包括两次公开会议和大量书面材料的提交,所有这些都在其相关委员会开会时在多塞特郡举行。它还收到了其环境服务总监的报告和县生态学家的建议。主任在其报告中考虑了申请人在自然保护的特定领域进行的环境影响评估(EIA)工作是否适当,并提出了拟议的缓解措施。报告的结论是,只要这些措施得到充分保障,就可以认为在这种特殊情况下,规划机构可以合理和合理地得出结论,对受保护物种或重要的自然保护区不会产生重大不利影响。

著录项

相似文献

  • 外文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号