Waltham Forest LBC v Oakmesh Ltd and Family Housing Association

机译:沃尔瑟姆森林(Waltham Forest)LBC v Oakmesh Ltd和家庭住房协会

获取原文
获取原文并翻译 | 示例
           

摘要

The claimant sought summary judgment against the defendants for an injunction to enforce an obligation (the obligation), contained in an agreement (the agreement) made pursuant to s.106 of the Town and Country Planning Act 1980 (the Act). The first defendant (Oakmesh) did not appear. The second defendant (Family) sought to amend its defence to advance a new argument that, on its true construction, the agreement was not one to which s.106 of the Act in fact applied.rnIn May 1996, the claimant resolved to grant planning permission for residential development of a site, subject to the completion of a s.106 agreement with the developer to ensure the provision of a footpath link through the development including the provision of a ramped footbridge link. On December 20,1996, Oakmesh took a transfer of the development site. It also took a transfer from Railtrack of an adjacent strip of land on which the bridge link was to be constructed. On the same day, planning permission was formally granted for residential development of the site and the agreement was formally entered into by deed between Oakmesh and the claimant. Also on the same day, Oakmesh transferred the site to Family, but not the strip of land acquired from Railtrack. In November 2000, the claimant entered into an agreement under s.38 of the Highways Act 1980 to adopt the roads and footways on the development (the s.38 agreement). Oakmesh failed to construct the bridge link.
机译:索赔人针对根据1980年《城市与乡村规划法》(该法)第106条订立的协议(协议)中包含的强制执行一项义务(义务)的禁令,对被告寻求简易判决。第一被告(Oakmesh)没有出现。第二个被告(家庭)试图修改其辩护,以提出新的论点,即在其真实解释上,该协议实际上并未适用该法第106条。rn 1996年5月,索赔人决定批准计划。批准进行场地的住宅开发,但须与开发商达成第106条协议,以确保通过开发项目提供人行道,包括提供倾斜的人行天桥。 1996年12月20日,Oakmesh转移了开发地点。它还从Railtrack转移了要在其上建造桥梁链接的相邻土地带。同一天,该场地的住宅开发获得了正式的规划许可,并且协议由Oakmesh与索赔人之间正式签订。也是在同一天,Oakmesh将场地转移给了Family,但没有将其从Railtrack手中获得。 2000年11月,索赔人根据1980年《公路法》第38条订立了一项协议,以采纳发展的道路和人行道(第38条协议)。 Oakmesh无法构建网桥链接。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号