Excavation of Centre Gullet, Widening and Benching of Underground Machine Hall of Teesta (Stage V) Hydroelectric Project, East Sikkim

机译:锡金东部Teesta(V期)水电项目中心机沟开挖,地下机房加宽和台阶

获取原文
获取原文并翻译 | 示例

摘要

This paper presents the blast design, supports and sequence of excavation for centre gullet, widening operations of underground machine hall to its full -width and depth (benching). The average progress, pull obtained per round of blast, was 90% and the hole blast impressions observed after blast were more than 80% of the actual drilled length. The progress of centre gullet and side widening achieved were 40 m per month and 45 m per month, respectively. The average benching progress achieved was 12 000m~3 per month and maximum benching progress achieved was 18 000m~3 in a month. The recorded blast induced vibrations were within safe limits. The performance of blast and post-blast observations indicate that the drilling and the charging patterns followed for the aforesaid underground excavations were safe and efficient.
机译:本文介绍了中心沟的爆破设计,支护和开挖顺序,将地下机房的操作扩展到其整个宽度和深度(弯曲)。每轮爆破获得的平均拉力为90%,爆破后观察到的孔爆破痕迹超过实际钻孔长度的80%。中心食道和侧面加宽的进度分别为每月40 m和每月45 m。每月平均坐板进度为12000m〜3,每月最大坐板进度为18000m〜3。记录的爆炸引起的振动在安全范围内。爆破和爆破后的观察结果表明,上述地下挖掘的钻孔和装料方式是安全有效的。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号