首页> 外文期刊>Journal of Hydraulic Engineering >Case Study: Dam Safety during Construction, Lessons of the Overtopping Diversion Works at Aguamilpa Dam
【24h】

Case Study: Dam Safety during Construction, Lessons of the Overtopping Diversion Works at Aguamilpa Dam

机译:案例研究:施工期间的大坝安全,阿瓜米尔帕大坝的引水工程超前经验

获取原文
获取原文并翻译 | 示例
       

摘要

A study on risk analysis by overtopping of the diversion works of Aguamilpa Dam in Mexico was carried out to examine the overtopping event of January, 1992. Specifically, this study focuses on the upstream water surface elevation during the flood considering the tunnel discharge actual width and roughness. During this maximum flow event, the upstream cofferdam was overtopped and the discharge tunnels exceeded their maximum hydraulic capacity. The risk analysis was made considering the original hydrologic data (until 1992), the final constructed conditions, to establish a performance function that compares the risk of original deterministic analysis with a probabilistic analysis made in 1992. The study also focuses on practical improvements in the construction stage of tunnels; like lining the floor with hydraulic concrete and shotcrete in vaults and walls, that improves the safety of dams during construction and increases the real return period. The work here is presented as a case study because of the unique large-scale flow conditions that are registered in diversion works of dams.
机译:为了检查1992年1月的超车事件,对墨西哥Aguamilpa大坝的引水工程进行了超车风险分析研究。具体而言,该研究集中在洪水期间上游水面高程,考虑了隧道的排水实际宽度和粗糙度。在此最大流量事件期间,上游围堰超顶,出水隧洞超过其最大水力容量。进行风险分析时要考虑原始的水文数据(到1992年),即最终的构造条件,以建立一个性能函数,将原始确定性分析的风险与1992年进行的概率分析进行比较。隧道的施工阶段;例如在地板上铺上液压混凝土并在拱顶和墙壁中喷射混凝土,从而提高了施工期间大坝的安全性,并增加了实际的回收期。由于在大坝的引水工程中记录了独特的大规模流动条件,因此这里的工作是作为案例研究提出的。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号