Analysis of schedule deviations in road construction projects and the effects of project physical characteristics:

机译:分析道路建设项目中的进度偏差以及项目物理特性的影响:

获取原文
获取原文并翻译 | 示例
           

摘要

Purpose: This study aims to investigate the schedule deviation in road construction projects and the effect of project physical characteristics on schedule deviations. The study also addresses the main factors affecting time deviation in road construction projects. Design/methodology/approach: The study is based on a sample of 101 road construction projects awarded in the West Bank in Palestine over the years 2010-2015. The study investigates the time deviation in total project duration and the deviations in major activities of road construction projects: earthworks, base works and asphalt works. Based on the collected data, regression models are developed to show the relation between actual duration and estimated duration. The study also investigates the effect of project physical characteristics on time deviation through regression analysis. The considered characteristics are: project size, terrain conditions, ground conditions and soil quality. To identify the main factors affecting time deviation, a survey of 40 contractors and 30 consultants was performed. Findings: The study reveals the following: average of time deviations in earthworks = 46.48 per cent, average of time deviation in base works = 29.66 per cent, average of time deviation in asphalt works = 23.43 per cent and average of time deviation in total duration = 47.72 per cent. Regression models that investigate the effect of physical project characteristics (i.e. project size, terrain condition, ground condition and soil quality) on time deviation are discussed. The survey reveals that the top five factors affecting delay in road construction projects are political situation, payments delay by the owner, lack of coordination between construction parties, frequent change orders and unexpected ground condition and terrain. Originality/value: This study investigates the schedule deviation in road construction projects and the effect of project physical characteristics on schedule deviations. The study also addresses the main factors affecting time deviation in road construction projects. The study is based on field data collected from 101 road construction projects and a questionnaire survey conducted in the West Bank in Palestine. Based on the findings, a number of recommendations are formulated to control the problem of time deviation in construction projects. Although this study is specific to the country of Palestine, its results can be applicable to other developing countries facing similar problems in their public construction sectors.
机译:目的:本研究旨在调查道路建设项目中的进度偏差以及项目物理特性对进度偏差的影响。该研究还探讨了影响道路建设项目时间偏差的主要因素。设计/方法/方法:该研究基于2010-2015年在巴勒斯坦西岸获得的101个道路建设项目的样本。本研究调查了项目总工期的时间偏差以及道路建设项目主要活动(土方,基础工程和沥青工程)的偏差。基于收集的数据,开发回归模型以显示实际工期与估算工期之间的关系。该研究还通过回归分析研究了项目物理特征对时间偏差的影响。考虑的特征是:项目规模,地形条件,地面条件和土壤质量。为了确定影响时间偏差的主要因素,对40名承包商和30名顾问进行了调查。结果:研究发现:土方工程的时间偏差平均值为46.48%,基础工程的时间偏差平均值为29.66%,沥青工程的时间偏差平均值为23.43%,总工期的时间偏差平均值= 47.72%。讨论了研究物理项目特征(即项目规模,地形条件,地面条件和土壤质量)对时间偏差的影响的回归模型。调查显示,影响道路建设项目延误的前五个因素是政治局势,业主付款延误,施工方之间缺乏协调,频繁的变更单以及意外的地面条件和地形。独创性/价值:本研究调查了道路建设项目中的进度偏差以及项目物理特性对进度偏差的影响。该研究还探讨了影响道路建设项目时间偏差的主要因素。该研究基于从101个道路建设项目中收集的现场数据以及在巴勒斯坦西岸进行的问卷调查。基于这些发现,提出了一些建议来控制建筑项目中的时间偏差问题。尽管这项研究仅针对巴勒斯坦国,但其结果可适用于在公共建筑领域面临类似问题的其他发展中国家。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号