Purpose - The purpose of this study is to describe how the University of Minnesota's capital program implemented risk management metrics on 266 construction projects and to present the results of the risk metrics. Design/methodology/approach - The implementation of Weekly Risk Reports (WRR) on the university construction projects captured information on the internal and external efforts related to minimizing project risks. The report implemented captured project risks, management plans, cost changes and schedule delays. Findings - Findings reveal that the university was able to effectively capture project risk metrics through the WRR. The risk metrics identified the risks categories that impacted the 266 project costs and schedules. Through these findings, the university has a better understanding of how their internal stakeholders create the greatest risk to impacting the project cost and schedule. This paper presents the risk impacts collected from the 266 projects. Research limitations/implications - A complete analysis of the risk metrics was limited in this research due to the extensive measurements collected. Future analysis will provide additional findings from the risk information. Originality/value - The paper presents both the implementation and the risk management measurements used within a capital program of a major university to provide understanding of the common risks that are involved with capital projects.
机译:目的-这项研究的目的是描述明尼苏达大学的资本计划如何对266个建筑项目实施风险管理指标,并介绍这些风险指标的结果。设计/方法/方法-针对大学建设项目的每周风险报告(WRR)的实施捕获了有关将项目风险降至最低的内部和外部工作的信息。该报告实施了捕获的项目风险,管理计划,成本变更和进度延迟。调查结果-调查结果表明该大学能够通过WRR有效地捕获项目风险指标。风险度量确定了影响266个项目成本和进度的风险类别。通过这些发现,大学可以更好地了解其内部利益相关者如何对影响项目成本和进度产生最大风险。本文介绍了从266个项目中收集的风险影响。研究的局限性/意义-由于收集了广泛的度量,因此在这项研究中对风险指标的完整分析受到限制。将来的分析将提供有关风险信息的其他发现。原创性/价值-本文介绍了主要大学的资本计划中使用的实施和风险管理度量,以提供对资本项目涉及的常见风险的理解。

著录项

  • 来源
    《Journal of Facilities Management 》 |2014年第2期| 158-171| 共14页
  • 作者单位

    Performance Based Studies Research Group (PBSRG), School of Sustainable Engineering and the Built Environment, Arizona State University, Tempe, Arizona, USA;

    Performance Based Studies Research Group (PBSRG), School of Sustainable Engineering and the Built Environment, Arizona State University, Tempe, Arizona, USA;

    Performance Based Studies Research Group (PBSRG), School of Sustainable Engineering and the Built Environment, Arizona State University, Tempe, Arizona, USA;

  • 收录信息
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类
  • 关键词

    Performance measurement; Risk management; University; Capital program; Project risk;

    机译:绩效评估;风险管理;大学;基本计划;项目风险;

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号