Geostationary Weather Satellites: Progress Made, but Weaknesses in Scheduling, Contingency Planning, and Communicating with Users Need to Be Addressed

机译:对地静止气象卫星:已取得进展,但需要解决日程安排,应急计划和与用户沟通方面的缺陷

获取原文
获取原文并翻译 | 示例
       

摘要

The GOES-R program is well on its way toward developing the first satellite in the series, but it continues to face risks that could delay the first satellite's launch. Among these risks are issues we have previously raised on how the program manages reserve funds and implements sound scheduling practices. Specifically, the agency does not provide important details on its contingency reserve funds to senior executives, including the reserves allocated for each of the four satellites or key assumptions made in calculating reserves. Without this information, program officials could misinterpret the size of the remaining reserves and make poor decisions regarding the program's future funding. The agency has improved selected scheduling practices, but others remain weak-in part, according to agency officials, due to the dynamic nature of scheduling a program as complex as the GOES-R satellite program. As the agency closes in on its expected launch date, technical issues in developing the space and ground segments and scheduling problems could make it more difficult to launch on schedule, and program officials now acknowledge that the launch date may be delayed by 6 months. Any delay in the anticipated launch date would expand a potential one-year gap in the availability of an on-orbit backup GOES satellite, and raise the risk of a gap in geostationary satellite data should one of the two operational satellites experience a problem.
机译:GOES-R计划正在顺利开发该系列的第一颗卫星,但它仍面临着可能会延迟第一颗卫星发射的风险。在这些风险中,我们先前曾提出过有关该程序如何管理储备金和实施合理的调度惯例的问题。具体来说,该机构没有向高级管理人员提供有关其应急储备金的重要细节,包括分配给四个卫星中的每个卫星的储备金或在计算储备金时所作的关键假设。没有这些信息,计划官员可能会误解剩余储备金的规模,并对计划的未来资金做出错误的决定。该机构官员说,该机构已经改进了某些调度方法,但其他方面仍然薄弱,这是因为调度与GOES-R卫星程序一样复杂的程序具有动态性。由于该机构的预计发射日期即将截止,因此开发空间和地面部分的技术问题以及计划问题可能使按计划发射更加困难,计划官员现在承认发射日期可能会推迟6个月。预期发射日期的任何延迟都将扩大在轨备用GOES卫星在可用性方面可能存在的一年的间隔,并且如果两颗运行中的卫星之一遇到问题,则会增加对地静止卫星数据出现间隔的风险。

著录项

  • 来源
    《Journal of current issues in media and t》 |2014年第3期|253-295|共43页
  • 作者

  • 作者单位
  • 收录信息
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类
  • 关键词

  • 入库时间 2022-08-18 02:02:07

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号