Short-term production scheduling with non-triangular sequence-dependent setup times and shifting production bottlenecks

机译:短期生产调度,具有非三角形序列依赖的设置时间和转移生产瓶颈

获取原文
获取原文并翻译 | 示例
           

摘要

A novel mathematical model is introduced that allows solving real-life scheduling problems in complex multi-stage machine environment with (i) non-triangular sequence-dependent setup times and (ii) shifting production bottlenecks, both of which are important aspects appearing in varying manufacturing industries. The primary goal is to minimise the tardiness of customer orders, which may consist of multiple production orders each in turn composed of several batches. A secondary objective is to maximise the production capacity utilization as measured by the makespan. The model is elaborated for general animal-feed plants which have to deal with the particular production scheduling problem on a daily basis. Dispatching rules are introduced to enhance the optimization progress. Numerical experiments show that optimising the model leads to schedules that meet the due dates. Moreover, by reducing the mean idle time of production lines with 35.6%, the optimization leads to a makespan reduction of 6.5% on average compared to real-life applied schedules.
机译:介绍了一种新的数学模型,允许在复杂的多级机器环境中解决具有(i)非三角形序列依赖的设置次数和(ii)转换生产瓶颈的实际调度问题,这两者都是不同的重要方面制造业。主要目标是最大限度地减少客户订单的迟到,其中可能由多个生产订单组成,每个生产订单又由几个批次组成。次要目标是通过Makespan来最大化生产能力利用率。该模型用于一般动物 - 饲料厂,该植物每天必须处理特定的生产调度问题。介绍调度规则以增强优化进展。数值实验表明,优化模型导致符合应有日期的时间表。此外,通过减少35.6%的生产线的平均空转时间,与现实施法的时间表相比,优化与平均的薄片减少为6.5%。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号