Upgrade scheme goes ahead at Sylvenstein dam, Germany

机译:德国西尔文施泰因大坝的升级方案正在进行

获取原文
获取原文并翻译 | 示例
   

获取外文期刊封面封底 >>

       

摘要

The Sylvenstein dam, which provides flood protection for Bavaria, Germany, is to undergo an upgrade project, to ensure its stability. In May, the most extensive phase of the project went ahead, which included installing a 10 000 m2 diaphragm wall to seal the dam core, extending for a length of 170 m and reching a depth of 25 m beneath the dam into the former bed of the Isar river. A cutoff wall of this depth has not been constructed in Germany before, and this measure is being taken to ensure that the dam remains watertight. This work, scheduled for completion in November 2012, will be carried out by a Bauer BC 40 cutter unit mounted on a MC 128 base carrier, as well as two MC 64 foundation cranes for grab excavation and concreting. The contract is worth around € 11.5 million. The benefit of this dam, which is the largest single flood protection measure to be undertaken in Bavaria, was underlined by the State's Environment Minister, Dr Marcel Huber. He and Prof Thomas Bauer, Chairman of the specialist contractor for the cutoff, Bauer AG, celebrated the beginning of work on site on 25 May.
机译:为德国巴伐利亚州提供防洪保护的西尔文施泰因大坝将进行升级工程,以确保其稳定性。 5月,该项目最广泛的阶段进行了,其中包括安装一个10000 m2的隔膜墙以密封大坝核心,延伸170 m的长度,并在大坝下方将25 m的深度缩水至前河床。伊萨尔河。以前在德国尚未建造过这种深度的防渗墙,并且正在采取此措施以确保大坝保持水密性。这项工作计划于2012年11月完成,将由安装在MC 128底架上的Bauer BC 40切割机单元以及两台用于抓斗挖掘和浇筑的MC 64基础起重机进行。合同价值约1150万欧元。州环境部长马塞尔·胡贝尔(Marcel Huber)博士强调了该水坝的好处,这是巴伐利亚州最大的单一防洪措施。他和Bauer AG截断的专业承包商主席Thomas Bauer教授于5月25日庆祝现场工作的开始。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号