Analysis under way following saddle dam failure at Xe-Pian Xe-Namnoy, Lao

机译:老挝Xe-Pian Xe-Namnoy鞍坝溃坝后的分析

获取原文
获取原文并翻译 | 示例
       

摘要

The breach of a saddle dam at the 410 MW Xe-Pian Xe-Namnoy hydro project under construction in southern Laos has, according to the Lao Government, killed at least 11 people and left more than 7000 homeless. The project's Saddle Dam 'D' failed on the night of 23 July, releasing 0.5 x 10~9 m~3 of water from one of the project's two reservoirs in Attapeu province. As we went to press, rescuers were searching for more than 120 people still missing from the six villages destroyed immediately downstream of the dam.
机译:根据老挝政府的说法,在老挝南部正在建设的410兆瓦Xe-Pian Xe-Namnoy水电项目中,一座鞍式水坝的破坏造成至少11人死亡,并使7000多人无家可归。该项目的鞍形水坝“ D”在7月23日晚上失败,从该项目位于阿塔佩乌省的两个水库之一释放了0.5 x 10〜9 m〜3的水。在我们付印之时,救援人员正在寻找在大坝下游直接被摧毁的六个村庄中仍失踪的120多人。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号