Substantial Completion Under Common Law for Purposes of Nevada Statute of Repose Not Determined by Substantial Compliance With Specifications

机译:根据常规法律的惯例,即Nevada of Readose的惯例,而不是通过大量遵守规范确定

获取原文
获取原文并翻译 | 示例
           

摘要

The Supreme Court of Nevada ruled, in an action brought by a homeowners association against the developer for constructing defective rockery walls, that the claims were barred by the expiration of the state's six-year statute of repose. The court said that the six-year period began to run upon the substantial completion of the construction, the determination of which was separate from the determination of whether there was substantial compliance with the project specifications. Somersett Owners Association v. Somersett Development Company, LTD,-P.3d-, 2021 WL 3237184, 137 Nev. Adv. Op. 35, No. 79921 (Nev. July 29, 2021).
机译:内华达州最高法院裁定,在房主与开发商建造有缺陷的假山墙上带来的行动中,索赔被国家六年的休息时间到期禁止。 法院表示,六年期开始在建设的实质性完成后履行,决定与确定是否有大量遵守项目规范的决定分开。 Somersett所有者协会v。Somersett Development Company,Ltd,-P.3D-,2021 WL 3237184,137 Nev。adv。 op。 35,No.79921(Nev。7月29日,2021年)。

著录项

相似文献

  • 外文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号