首页> 外文期刊>Engineering news-record >RI Wind-Farm Subcontractor Slowly Ties Together Project
【24h】

RI Wind-Farm Subcontractor Slowly Ties Together Project

机译:RI风电场分包商缓慢合作项目

获取原文
获取原文并翻译 | 示例
       

摘要

After nearly four months of grueling work 50 ft beneath a state beach in Rhode Island, crews have finished drilling a 2,250-ft tunnel for the conduit that will carry power from the 30-MW Block Island wind farm to a National Grid switching station in Narragansett, R.I. David Graves, a spoke man for the energy provider to Rhode Island, New York and Massachusetts, says the completion on May 6 will allow the company to begin installation of undersea cable when New Jersey-based subcontractor LS Cable America wraps up installation of Deepwa-ter Wind cabling from five offshore turbines to the island. "We have had lousy weather and are at the mercy of the ocean, but we are prepared to begin laying our 20-mile stretch of cable from the mainland to the island on May 28," he says.
机译:经过在罗德岛州立海滩下方50英尺处进行了近四个月的艰苦工作之后,机组人员已经完成了一条2250英尺的隧道钻探,该隧道将把电力从30兆瓦的布洛克岛风电场输送到纳拉甘西特的国家电网交换站。 ,美国纽约州和马萨诸塞州罗德岛州能源供应商的发言人戴维·格雷夫斯(RI David Graves)表示,5月6日竣工后,该公司将可以在总部位于新泽西州的分包商LS Cable America完工安装海底电缆时开始安装海底电缆。从五个海上涡轮机到岛上的深水风缆。他说:“我们的天气糟糕,受海洋的约束,但我们准备从5月28日开始铺设从大陆到小岛的20英里长的电缆。”

著录项

  • 来源
    《Engineering news-record》 |2016年第14期|14-14|共1页
  • 作者

    Johanna Knapschaefer;

  • 作者单位
  • 收录信息 美国《工程索引》(EI);
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类
  • 关键词

  • 入库时间 2022-08-18 00:11:17

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号