首页> 外文期刊>IEEE Transactions on Dielectrics and Electrical Insulation >Basic aspects of partial discharge on-site testing of long length transmission power cables
【24h】

Basic aspects of partial discharge on-site testing of long length transmission power cables

机译:长距离输电电缆局部放电现场测试的基本方面

获取原文
获取原文并翻译 | 示例
           

摘要

More and more transmission power cable circuits with lengths up to several tens of kilometers will be installed and put into operation. This contribution discusses basic aspects of selecting an on-site test voltage and the partial discharge measurement under on-site testing conditions of power cable lines with long length. On the one side, the generation of suitable test voltages for high capacitive loads, especially long cables, is evaluated and experiences of on-site measurements are described. On the other hand, the challenges for sensitive partial discharge measurement on long length power cables are discussed. Under this scope, partial discharge measurement by dual-sided measurement technique is described and examples are shown.
机译:越来越多的传输电力电缆线路的长度将达到几十公里,并将投入使用。本贡献讨论了选择现场测试电压和在长距离电力电缆线的现场测试条件下进行局部放电测量的基本方面。一方面,评估了针对高电容性负载(尤其是长电缆)的合适测试电压的生成,并描述了现场测量的经验。另一方面,讨论了在长电缆上进行敏感局部放电测量的挑战。在此范围内,描述了通过双面测量技术进行的局部放电测量并示出了示例。

著录项

  • 来源
  • 作者单位

    Institute of Power Transmission and High Voltage Technology (IEH), University of Stuttgart, Paffenwaldring 47, 70569 Stuttgart, Germany;

    Institute of Power Transmission and High Voltage Technology (IEH), University of Stuttgart, Paffenwaldring 47, 70569 Stuttgart, Germany;

    onsite hv solutions ag, Töpferstrasse 5, 6004 Luzern, Switzerland;

    onsite hv solutions ag, Töpferstrasse 5, 6004 Luzern, Switzerland;

  • 收录信息 美国《科学引文索引》(SCI);美国《工程索引》(EI);
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类
  • 关键词

    Partial discharges; Power cables; Testing;