Relationship between pit slope design and coal reserve estimation in Pit X, Muara Enim, South Sumatra Province

机译:南苏门答腊省坑X坑斜坡设计与煤炭储备估计的关系

获取原文
           

摘要

Mine planning is an important part of mining activity. Improper mine plan will increase production costs, non-optimal extraction of mines and safety factors that do not meet the standard. One of the most important aspects before undertaking mine plan is determining the optimal slope design as a basis for making mine pits for coal extraction. This study aims to estimate the maximum reserves that can be taken from the mine pit by taking account of the safety factor of the pit slope design. The study was conducted using drill log data and rock engineering characteristics. Analysis of slope stability is done using the Rocscience Slide V.6 software while coal reserves estimation is done using Minescape V.5.2. Slope stability analysis is modeled with several scenarios of slope angles until a single optimal slope angle is obtained, with the value of the slope safety factor that meets the safety criteria. The results showed that the maximum single slope angle in a safe pit was 52° with a safety factor of 1.266, while the coal reserves obtained with the said slope angle are 29, 965, 008 tons.
机译:矿山规划是采矿活动的重要组成部分。矿山规划不当将提高生产成本,不适合提取矿山和不符合标准的安全因素。承担矿山计划之前最重要的一个方面是确定最佳斜坡设计作为制造煤炭提取的矿坑的基础。本研究旨在通过考虑坑坡设计的安全系数来估计可以从矿坑中取出的最大储备。该研究采用钻头数据和岩石工程特性进行。利用储量估计使用MINESCAPE V.5.2进行煤炭储备估计,采用Rocscience Slide V.6软件进行分析。坡度稳定性分析用若干斜率角度建模,直到获得单个最佳倾斜角度,具有满足安全标准的斜率安全系数的值。结果表明,安全坑中的最大单斜率角为52°,安全系数为1.266,而具有上述斜角的煤炭储量为29,965,008吨。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号