Simulation Method for Scheduling Linear Construction Projects Using the Learning– Forgetting Effect

机译:学习与遗忘效应对线性建设项目进行调度的仿真方法

获取原文
           

摘要

Linear projects such as highways, multi-storey buildings or pipelines are implemented by repeating the sequences of processes on units. Repetitive operations affect acquiring more and more experience, which shortens the duration of subsequent activities. On the other hand, the possible breaks in work make this effect disappear. Breaks at work are most often caused by the lack of crew work continuity. While delaying the subsequent sequences of processes properly, it is possible to reduce interruptions and limit the forgetting effect. A simulation method for scheduling linear construction projects has been developed, taking into account the learning and forgetting effect. It allows to increase the probability of the crew work continuity while meeting the project deadline with a specific probability. As a result, the estimation of the project duration is more accurate, which may provide an advantage at the stage of submitting offers in tenders for construction works.
机译:线性项目,例如高速公路,多层建筑物或管道,是通过重复单元上的过程序列来实现的。重复的操作会影响获得越来越多的经验,从而缩短了后续活动的持续时间。另一方面,可能的工作中断会使这种影响消失。工作中断通常是由于缺乏机组人员的工作连续性造成的。在适当地延迟后续处理序列的同时,可以减少中断并限制遗忘效果。考虑到学习和遗忘的影响,开发了一种模拟线性建筑项目进度的仿真方法。它可以增加机组人员连续工作的可能性,同时以特定的概率满足项目截止日期。结果,对项目工期的估计更加准确,这可能在为建筑工程招标的阶段提供优势。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号