首页> 外文期刊>Journal of Energy Technologies and Policy >Impact of Automatic Circuit Reclosers and Distributed Generators on the Reliability Indices of Electrical Distribution Systems
【24h】

Impact of Automatic Circuit Reclosers and Distributed Generators on the Reliability Indices of Electrical Distribution Systems

机译:自动重合闸和分布式发电机对配电系统可靠性指标的影响

获取原文
           

摘要

Reliability is the ability of power system to perform its intended function as at when due. Parameters used to assess the level at which this is done are called reliability indices. Previous researches have not focused deeply on the effect of installing automatic circuit reclosers ACRs and distributed generators (DGs) on the assessment of reliability indices of electrical power distribution system, hence, the drive towards this research paper. Monte Carlo Simulation (MCS) was performed in MATLAB on the IEEE 34 test feeder. Under three different case studies- when one ACF was installed on the test system, when two ACRs were installed on the test system and when 1MW DG unit was installed on the test system. Real system data were used as input parameters for the simulation. The overall distribution system reliability was evaluated using the load point and the system reliability indices such as System Average Interruption Frequency Index (SAIFI), System Average Interruption Duration Index (SAIDI) and Customer Average Interruption Duration Index (CAIDI). (CAIDI), Average Service Availability Index (ASAI) and EUE.The results obtained with the MCS were compared with the results obtained previously for the same test system using analytical approach and was found to be in agreement. The results of the research paper showed that the installation of an automatic circuit recloser gave a reduction in SAIFI value from 17.33hours/year to 14.93 hours/year with the installation of ACR between nodes (800-802). The best improvement was noticed when ACR was installed between nodes (834-842) in the electrical feeder. The value of SAIDI obtained also decreased from 8.90hom/year to 7.99 hours/year with the installation ACR between nodes (800-802). When two ACR were installed in the test system between nodes (828-824) and (824-826), the values obtained for SAIFI were 10.74 hours/year and 11.20 hours/year respectively representing a level of improvement in the SAIFI index. Between these nodes, values of SAIFI were also 4.211 hours/year and 4.423 hours/year which also represents an improvement in SAIDI values.Installation of 1MW Distributed generator (DG) unit in the test system gave SAIFI and SAIDI values of 14.23 hours/year and 5.80 hours/year respectively representing an improvement in there two indices compared to when ACRs were installed at anywhere in the test system. The values obtained for ASAI for different locations of the 1MW DG unit fluctuate throughout the case descriptions. With the installation of the 1MW DG unit between nodes 834-842, 844-846, 834-860, 836-840, and 862-838, the values obtained for ASAI were 5.196, 5.101, 5.012, 6.141 and 6.128 respectively which represent appreciable level of improvement as compared to the base case. With the installation of one DG in the test system, the value obtained for the EUE was 17709kw. With the additional installation of ACR between nodes (846-848), (862-832), (888-890) and (854-856), the values obtained for EUE were 1152 kW, 11926 kW, 13146 kW and 14191 kW respectively indicating a level of reductions in the values of EUE. The ACRs, once installed optimally on the test system improves the reliability of the distribution system by isolating the healthy parts of the system automatically, which maintains the service to a substantial number of customers and reduce the repair time. The integration of DGs into the distribution test system provides the opportunity of operating the distribution system as a microgrid, allowing continuity of service in the network. It also forms a useful basis for evaluating the reliability of distribution feeders.
机译:可靠性是电力系统在到期时执行其预期功能的能力。用于评估完成级别的参数称为可靠性指标。以前的研究还没有深入研究安装自动电路重合闸ACR和分布式发电机(DG)对配电系统可靠性指标的评估,因此,本研究的驱动力。蒙特卡罗模拟(MCS)在MATLAB上的IEEE 34测试馈送器上执行。在三个不同的案例研究下-测试系统上安装了一个ACF,测试系统上安装了两个ACR,测试系统上安装了1MW DG单元。实际系统数据用作模拟的输入参数。使用负载点和系统可靠性指标(例如系统平均中断频率指数(SAIFI),系统平均中断持续时间指数(SAIDI)和客户平均中断持续时间指数(CAIDI))评估配电系统的整体可靠性。 (CAIDI),平均服务可用性指数(ASAI)和EUE。将使用MCS获得的结果与以前使用分析方法在同一测试系统中获得的结果进行比较,结果是一致的。研究结果表明,在节点之间安装ACR(800-802)时,安装自动重合闸可使SAIFI值从17.33小时/年降低到14.93小时/年。将ACR安装在电气馈线的节点(834-842)之间时,可以看到最佳的改进。通过在节点之间安装ACR(800-802),获得的SAIDI值也从8.90hom /年降低到7.99小时/年。当在节点(828-824)和(824-826)之间的测试系统中安装了两个ACR时,获得的SAIFI值分别为10.74小时/年和11.20小时/年,代表SAIFI指数的提高水平。这些节点之间的SAIFI值分别为4.211小时/年和4.423小时/年,这也表明SAIDI值有所提高。在测试系统中安装1MW分布式发电机(DG)单元后,SAIFI和SAIDI值为14.23小时/年和5.80小时/年分别表示与在测试系统中任何地方安装ACR相比,这两个指标都有所改善。在整个案例描述中,针对1MW DG单元不同位置的ASAI获得的值会有所波动。通过在节点834-842、844-846、834-860、836-840和862-838之间安装1MW DG装置,获得的ASAI值分别为5.196、5.101、5.012、6.141和6.128。与基本案例相比的改进水平。通过在测试系统中安装一个DG,获得的EUE值为17709kw。通过在节点(846-848),(862-832),(888-890)和(854-856)之间额外安装ACR,获得的EUE值分别为1152 kW,11926 kW,13146 kW和14191 kW表示EUE值降低的程度。 ACR一旦最佳安装在测试系统上,就可以通过自动隔离系统的正常运行部分来提高配电系统的可靠性,从而为大量客户维持服务并减少维修时间。将DG集成到配电测试系统中提供了将配电系统作为微电网运行的机会,从而使网络中的服务保持连续性。它还为评估配电馈线的可靠性提供了有用的基础。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号