Method Cement Post-grouting to Increase the Load Capacity for Bored Pile

机译:方法进行水泥后注浆,以增加钻孔桩的承载能力

获取原文
           

摘要

Drilled shafts foundations are used as an indispensable solution for long span bridges in Vietnam. In order to increase the bearing capacity, aside from the increasing of the pile length and diameter, an interested way now is treatment of pile bases after concrete placement. This study is aimed at investigating the defect at the bottom of the bored pile from the sonic test. The injection of hight pressure of cement grout to the shaft and tip of the defected bored pile was conducted to increase the bearing capacity of pile. The bearing capacity of defected bored pile is calculated by the TCXD-205:1998 an finite element mothod. After post-grouting technique done, the soil investigation tests have been carried out to define the properties of treated soils. The analytic mothod, finite element method an load test also have been applied to determine the bearing capacity of treated bored pile. The results show that the post-grouting to the shaft and tip of pile can increase two times of bearing capacity of defected bored pile and about 20% compared to the normal bored pile.
机译:钻孔轴基础是越南大跨度桥梁必不可少的解决方案。为了增加承载能力,除了增加桩长和直径之外,现在一种有趣的方法是在混凝土浇筑后处理桩基。这项研究的目的是从声波测试中研究钻孔桩底部的缺陷。将水泥浆高压注入有缺陷的钻孔桩的井筒和井顶,以增加桩的承载能力。缺陷桩的承载力是通过TCXD-205:1998有限元法计算的。在完成后灌浆技术之后,已经进行了土壤调查测试以定义处理过的土壤的特性。解析方法,有限元法和载荷试验也已应用于确定已处理钻孔桩的承载能力。结果表明,对桩身和桩端进行后灌浆可以使缺陷钻孔桩的承载能力提高两倍,比普通钻孔桩提高约20%。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号