Analysis and Evaluation of Mechanized Greenhouse Construction Project using CPM Methods

机译:基于CPM方法的机械化温室建设项目分析与评价

获取原文
           

摘要

In this study, the application of project scheduling for analysis and evaluation of mechanized greenhouse construction project was studied using Critical Path Method (CPM) with WinQsb software. This study was conducted in Khuzestan province of Iran. The results showed that the minimum completion time of this project, based on using CPM method, normal time and crash time is 201 and 137 days, respectively. Normal cost and crash cost are 3102665000 and 3187740000 Rials, respectively. Also cost slope in CPM method is 1329300 Rials that it means cost of reducing one day of the project completion time is 1329300 Rials. So results of CPM method showed that the cost of reducing the project completion time, to 180 days is 1600000 Rials.
机译:在这项研究中,使用WinQsb软件使用关键路径法(CPM)研究了项目进度在机械化温室建设项目分析和评估中的应用。这项研究是在伊朗胡兹斯坦省进行的。结果表明,基于CPM方法,该项目的最短完成时间为正常时间和崩溃时间,分别为201天和137天。正常费用和崩溃费用分别为3102665000里亚尔和3187740000里亚尔。另外,CPM方法的成本斜率是1329300里亚尔,这意味着减少项目完成时间一天的成本是1329300里亚尔。因此,CPM方法的结果表明,将项目完成时间减少至180天的成本为160万里亚尔。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号