The paper presents results of flow calculations for the Warta River on a reach of the Poznań Waterways System (PWS), conducted using the SPRUNER computer system of unsteady flow routing. The mathematical model of the 136.3 km reach of the Warta River started at the gauging section in Nowa Wie? Podgórna (km 342+600) and ended at the gauging section in Oborniki (km 206+300). Calculations have been conducted for steady flow conditions for five typical flows with given probabilities. Five variants of reconstruction of the Chwaliszewo Meander have been proposed. In each variant the split between the main Warta channel and the Chwaliszewo Meander channel was proposed at section 243+010, and both channels were to meet again at km 242+290, in the area of the river port. The section being reconstructed was 800 m long. The slope has been assumed to be 0.13‰ and was identical to that of the main channel of the Warta on this channel reach.
机译:本文介绍了在波兹南水道系统(PWS)的作用范围内使用非定常水流路由系统SPRUNER计算机系统进行的瓦尔塔河水流计算结果。瓦尔塔河长136.3公里的数学模型始于Nowa Wie? Podgórna(342 +600公里),结束于Oborniki(206 + 300公里)的测量区。对于具有给定概率的五个典型流,已经针对稳态流条件进行了计算。已提出了Chwaliszewo Meander重建的五个变体。在每个变体中,在第243 + 010节中提出了在Warta主河道和Chwaliszewo蜿蜒河道之间进行划分的建议,两条河道都将在河港地区再次在242 + 290公里处汇合。正在重建的部分长800 m。斜率被假定为0.13‰,并且与该通道段上Warta主通道的斜率相同。

著录项

获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号