首页> 外文期刊>Applied Sciences >Assessing and Prioritising Delay Factors of Prefabricated Concrete Building Projects in China
【24h】

Assessing and Prioritising Delay Factors of Prefabricated Concrete Building Projects in China

机译:评估和确定中国预制混凝土建筑项目的延期因素

获取原文
           

摘要

Prefabricated construction has been widely accepted as an alternative to conventional cast-in-situ construction, given its improved performance. However, prefabricated concrete building projects frequently encounter significant delays. It is, therefore, crucial to identify key factors affecting schedule and explore strategies to minimise the schedule delays for prefabricated concrete building projects. This paper adopts the decision-making trial and evaluation laboratory (DEMATEL) model and analytic network process (ANP) method to quantify the cause-and-effect relationships and prioritise the key delay factors in terms of their importance in the Chinese construction industry. The DEMATEL model evaluates the extent to which each factor impacts other factors. The quantified extents are then converted into a prioritisation matrix through ANP. The delay factors of prefabricated construction projects are selected and categorised based on a literature review and an expert interview. Questionnaires are then implemented to collect the data. The results reveal that the issue of inefficient structural connections for prefabricated components is found to be the most significant factor and most easily affected by other delay factors. This research also suggests prioritising major delay factors, such as ‘lack of communication among participants’ and ‘low productivity’, in the Chinese construction industry during scheduling control. Overall, this research contributes an assessment framework for decision making in the scheduling management of prefabricated construction.
机译:预制结构由于其改进的性能而被公认为是传统现浇结构的替代方案。但是,预制混凝土建筑项目经常遇到重大延误。因此,至关重要的是要确定影响进度的关键因素,并探索策略以最大程度地减少预制混凝土建筑项目的进度延迟。本文采用决策试验与评估实验室(DEMATEL)模型和分析网络过程(ANP)方法来量化因果关系,并根据关键延迟因素在中国建筑业中的重要性来确定其优先级。 DEMATEL模型评估每个因素影响其他因素的程度。然后通过ANP将量化的范围转换为优先级矩阵。预制建筑项目的延迟因素是在文献综述和专家访谈的基础上进行选择和分类的。然后实施问卷调查以收集数据。结果表明,预制构件的结构连接效率低下的问题是最重要的因素,并且最容易受到其他延迟因素的影响。这项研究还建议在计划控制期间,优先考虑中国建筑行业的主要延迟因素,例如“参与者之间缺乏沟通”和“生产率低下”。总的来说,这项研究为预制建筑的进度管理中的决策制定了评估框架。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号