首页> 外文期刊>Concrete >North Downs Tunnel, Channel Tunnel Rail Link: secondary lining
【24h】

North Downs Tunnel, Channel Tunnel Rail Link: secondary lining

机译:北唐斯隧道,海峡隧道铁路连接:辅助衬砌

获取原文
获取原文并翻译 | 示例
       

摘要

Site-batching proved to be a wise decision, affording tighter control and improved availability. Close contact between the technical and production teams enabled the materials to work. The choice of pfa proved beneficial in terms of heat reduction and concrete cohesive-ness. Other benefits were obtained from using recycled water and hot water when conditions dictated. The result was a secondary lining concrete that gained good early strengths so the cycle time was always achieved with no loss of pour due to lack of striking strength. These were all major contributions towards the achievement of production rates and project completion ahead of programme (see Figure 5).
机译:现场批处理被证明是明智的决定,它提供了更严格的控制并提高了可用性。技术团队和生产团队之间的密切联系使材料可以正常工作。 pfa的选择在降低热量和混凝土的粘结性方面被证明是有益的。在条件许可的情况下,使用循环水和热水可获得其他好处。结果是二次衬砌混凝土获得了良好的早期强度,因此,由于没有敲击强度,因此可以始终实现循环时间而不会倒水。这些都是对在计划之前实现生产率和项目完成的主要贡献(见图5)。

著录项

  • 来源
    《Concrete》 |2003年第4期|p.19-21|共3页
  • 作者

    Mark Aldam;

  • 作者单位

    Eurolink Joint Venture;

  • 收录信息 美国《工程索引》(EI);
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类 建筑科学;
  • 关键词

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号