A new slab production line installed at the old location Production starts running again after just nine months

机译:在原位置安装了一条新的板坯生产线,仅用了9个月,生产就重新开始运行

获取原文
获取原文并翻译 | 示例
   

获取外文期刊封面封底 >>

       

摘要

Caused by a technical failure, at Rinn in Heuchelheim/ Germany a hall of the slab production was destroyed entirely by fire in June 2008. Just in peak season when there is a great demand for concrete products for garden design Rinn had to react very quickly. However, thanks to a network of suppliers across Germany, which produced according to the specifications of Rinn, they maintained their ability to deliver. Now, the hall together with the new production line has been completed after a construction period of just nine months and the production is running again.
机译:由于技术故障,2008年6月在德国Heuchelheim的Rinn楼板生产大厅完全被大火烧毁。正值旺季,对花园设计用混凝土产品的需求很大,Rinn必须迅速做出反应。但是,得益于整个德国的供应商网络(根据Rinn的规范进行生产),他们保持了交付的能力。现在,经过短短九个月的建设,该大厅和新的生产线就已经完成,生产又重新开始了。

著录项

  • 来源
    《Betonwerk + Fertigteil-Technik》 |2009年第5期|50-51|共2页
  • 作者

  • 作者单位
  • 收录信息 美国《工程索引》(EI);
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类
  • 关键词

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号