During 2015 Victory House engaged RGB P&C Ltd to construct a hotel in Leicester Square, central London. The works were delayed and in March 2017 the parties entered into a emorandum of understanding (MOU). In July 2017 RGB issued interim application for payment no. 30, seeking a payment of £819,363.46 including VAT in addition to the £8.5m that it had already been paid. Victory House assumed that the MOU terms applied and declined to issue either a payment notice or a payless notice. RGB commenced adjudication.