Patrick Stevedores Operations No 2 Pty Ltd v McConnell Dowell Constructors (Aust) Pty Ltd

机译:Patrick Stevedores Operations No 2 Pty Ltd诉McConnell Dowell Constructors(Aust)Pty Ltd

获取原文
获取原文并翻译 | 示例
       

摘要

Contract - Building and Construction Industry Security of Payment Act 1999 (NSW) - construction work - reference dates - withdrawal of adjudication application - jurisdictional error The parties entered into a contract by which McConnell Dowell was to construct, test, and commission certain civil works. The contract provided progress claims to be submitted on the last day of each month for work performed to the second last day of that month. The contract also gave Patrick a right to terminate for convenience and, if it did so, McConnell Dowell was entitled to be paid under four separate heads: (1) for work carried out prior to the date of termination, it was entitled to be paid what would have been payable if the contract had not been terminated and McConnell Dowell had submitted a payment claim on the date of termination; (2) the cost of plant and materials reasonably ordered; (3) the reasonable cost of removing equipment from the site; and (4) a stated lump sum amount.
机译:合同-《 1999年建筑业和建造业付款安全法》(NSW)-建筑工程-参考日期-撤销裁决申请书-管辖权错误当事人签订了一份合同,麦康奈尔·杜威尔将根据该合同进行建筑,测试和委托某些土建工程。合同提供了进度索赔,该索赔要在每个月的最后一天提交,直到该月的第二天为止。合同还赋予Patrick方便而终止的权利,如果这样做,则McConnell Dowell有权在四个单独的标题下支付:(1)对于在终止日期之前进行的工作,它有权获得支付如果合同没有终止并且麦康奈尔·道威尔在终止之日提交了付款索赔,应支付的费用; (二)合理定购的厂房和材料费用; (3)从现场移走设备的合理费用; (4)规定的总付金额。

著录项

相似文献

  • 外文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号