首页> 外文期刊>Automation in construction >Heuristic algorithm for ready-mixed concrete plant scheduling with multiple mixers
【24h】

Heuristic algorithm for ready-mixed concrete plant scheduling with multiple mixers

机译:多搅拌机预拌混凝土厂调度的启发式算法

获取原文
获取原文并翻译 | 示例
           

摘要

In this study, the problem of integration of ready-mixed concrete (RMC) production scheduling and truck and pump dispatching in an RMC plant with multiple mixers is focused upon. A time-space network model, which combines RMC production and vehicle dispatching, is proposed. A heuristic algorithm with eight sets of conjoint priority rules for production scheduling, truck and pump dispatching, and mixer scheduling is developed to solve the problem. Computational experiments are conducted on actual cases collected from an RMC company; these cases are classified into four types based on the quantity of orders from construction sites and the discrete degree of construction sites. The advantages and disadvantages of adopting various conjoint-rules in the various types of cases are determined. The experimental results demonstrate that this heuristic solution is capable of enabling managers of RMC plants to develop more suitable schedules in various types of practical cases.
机译:在这项研究中,重点解决了在具有多个搅拌机的RMC工厂中预拌混凝土(RMC)生产调度与卡车和泵调度的集成问题。提出了一种将RMC生产与车辆调度相结合的时空网络模型。为解决该问题,开发了一种具有八组联合优先级规则的启发式算法,用于生产调度,卡车和泵调度以及搅拌机调度。对从RMC公司收集的实际案例进行了计算实验;根据来自施工现场的订单数量和施工现场的离散程度,将这些案例分为四种类型。确定了在各种类型的案例中采用各种联合规则的优缺点。实验结果表明,这种启发式解决方案能够使RMC工厂的经理在各种实际案例中制定更合适的时间表。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号