A Robust optimization approach to assess the effect of delays in the connection-to-the-grid time of new generation power plants over transmission expansion planning

机译:一种鲁棒的优化方法,用于评估新一代发电厂的并网时间延迟对输电扩容计划的影响

获取原文
获取原文并翻译 | 示例
       

摘要

Construction times of new power plants are subject to uncertainty in deregulated electricity markets and they have an important impact on the planning of the expansion of the transmission network. In this paper, we develop a model of transmission expansion planning that is based on Robust optimization and considers the uncertainty in the instant when new power plants are connected into the electricity grid. Using this transmission expansion planning model, we assess the impact of postponing the connection time of some new power plants over the system cost and the optimal network expansion plan. By obtaining the optimal solutions of the proposed model for different levels of robustness, we are able to rank the new power plants with respect to how much the delay of each project negatively affects the system cost. We illustrate our methodology and the performance of two solution approaches proposed to solve our model by using a 34-node stylized version of the main Chilean grid. In the case of the main Chilean grid, the results obtained indicate that some of the projects whose delays negatively affect the most to the system cost are the renewable power plants projected for the next ten years. This is important from the regulator viewpoint because it allows the assessment of renewable energy policies that accelerate the installation of renewable new power plants also in terms of their impact over the transmission expansion planning.
机译:新电厂的建设时间受电力市场放松管制的不确定性的影响,它们对输电网络的扩展规划具有重要影响。在本文中,我们建立了基于鲁棒优化的输电扩展计划模型,并考虑了新电厂并网时的不确定性。使用这种传输扩展计划模型,我们评估了推迟一些新电厂的连接时间对系统成本和最佳网络扩展计划的影响。通过获得针对不同鲁棒性水平的拟议模型的最佳解决方案,我们能够针对每个项目的延迟对系统成本产生负面影响的程度对新电厂进行排名。我们通过使用智利主网格的34节点风格化版本说明了我们的方法论以及为解决模型而提出的两种解决方案方法的性能。对于智利的主要电网,所获得的结果表明,延迟对系统成本影响最大的一些项目是未来十年的可再生能源发电厂。从监管者的角度来看,这一点很重要,因为它可以评估可再生能源政策,这些政策还可以根据对输电扩展计划的影响来加速新可再生能源电厂的安装。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号