首页> 外文学位 >Pile setup, Dynamic construction control, and Load and Resistance Factor Design of vertically-loaded steel H-piles.
【24h】

Pile setup, Dynamic construction control, and Load and Resistance Factor Design of vertically-loaded steel H-piles.

机译:竖向加载的H型钢桩的桩设置,动态施工控制以及荷载和阻力系数设计。

获取原文
获取原文并翻译 | 示例

摘要

Because of the mandate imposed by the Federal Highway Administration (FHWA) on the implementation of Load Resistance Factor Design (LRFD) in all new bridge projects initiated after October 1, 2007, research on developing the LRFD recommendations for pile foundations that reflect local soil conditions and construction experiences for the State of Iowa becomes essential. This research focuses on the most commonly used steel H-pile foundation. The research scope is to (1) characterize soil-pile responses under pile driving impact loads, and (2) understand how the generated information could be used to improve design and construction control of piles subjected to vertical loads in accordance with LRFD.;It has been understood that efficiency of the pile foundation can be elevated, if the increase in pile resistance as a function of time (i.e., pile setup) can be quantified and incorporated into the LRFD. Because the current pile foundation practice involves different methods in designing and verifying pile performances, the resulting discrepancy of pile performances often causes an adjustment in pile specifications that incurs incremental construction costs, significant construction delays, and other associated scheduling issues. Although this research focuses on the most advanced dynamic analysis methods, such as Pile Driving Analyzer (PDA), Wave Equation Analysis Program (WEAP), and CAse Pile Wave Analysis Program (CAPWAP), the accuracy of these methods in estimating and verifying pile performances is highly dependent upon the input selection of dynamic soil parameters that have not been successfully quantified in terms of measured soil properties.;To overcome these problems and due to the limited data available from the Iowa historical database (PILOT), ten full-scaled field tests on the steel H-piles (HP 250 x 63) were conducted in Iowa. Detailed in-situ soil investigations using the Standard Penetration Test (SPT) and the Cone Penetration Test (CPT) were completed near test piles. Push-in pressure cells were installed to measure total lateral earth and pore water pressures during the life stages of the test piles. Soil characterization and consolidation tests were performed. Pile responses during driving, at the end of driving (EOD), and at restrikes were monitored using PDA. PDA records were used in CAPWAP analysis to estimate the pile performances. In addition, hammer blow counts were recorded for WEAP analysis. After completing all restrikes, static load tests were performed to measure the pile resistance.;The information collected from the tests provided both qualitative and quantitative studies of pile setup. Unlike the empirical pile setup methods found in the literature, analytical semi-empirical equations are developed in terms of soil coefficient of consolidation, SPT N-value, and pile radius to systematically quantify the pile setup. These proposed equations do not require the performance of pile restrikes or load tests; both are time consuming and expensive. The successful validation of these proposed equations provides confidence and accuracy in estimating setup for steel H-piles embedded in cohesive soils. For the similar study on large displacement piles, the results indicate that the proposed methods provide a better pile setup prediction for smaller diameter piles.;Based on statistical evaluations performed on the available database, field tests, and sources found in the literature, it was determined that different uncertainties were associated with the estimations of the initial pile resistance at the EOD and pile setup resistance. To account for this difference, a procedure for incorporating the pile setup in LRFD was established by expanding the First Order Second Moment (FOSM) method, while maintaining the same target reliability level. The outcome of the research provides a methodology to determine resistance factors for both EOD and setup resistances based on any regional database. Therefore, the practical implementation of pile setup can now be included in a pile design, which has not been provided in the latest American Association of State Highway and Transportation Officials (AASHTO) Bridge Design Specifications.;Combining the PILOT database with the field test results, regionally calibrated resistance factors for bridge deep foundations embedded in clay, sand, and mixed soil profiles were established for the dynamic analysis methods. This regional calibration generated higher resistance factors and improved the efficiency of pile performances when compared with those recommended by the latest AASHTO Bridge Design Specifications. Furthermore, using these calibrated results of the dynamic analysis methods that serve as the construction control methods, the resistance factors of the Iowa in-house method (Iowa Blue Book) that serves as the design method were enhanced through the development of a construction control procedure. Construction control consideration minimizes the discrepancy between design and field pile resistances, and integrates the construction control methods as part of the design process.;An improved CAPWAP signal matching procedure was developed to provide a better quantification of the dynamic soil damping factor and quake value with respect to different soil properties along the shaft and at the toe of a pile. Correlation studies resulted in the development of several empirical equations for quantifying the dynamic soil parameters using the measured SPT N-value. In addition, the results reveal the influences of pile setup and pile installation on the dynamic soil parameters. The application of these estimated dynamic soil parameters was validated through the improvement of a CAPWAP signal match quality.
机译:由于联邦公路管理局(FHWA)对在2007年10月1日之后启动的所有新桥梁项目中实施抗荷载因子设计(LRFD)的强制性规定,因此需要研究针对反映当地土壤状况的桩基础制定LRFD建议爱荷华州的建设经验变得至关重要。这项研究的重点是最常用的钢H桩基础。研究范围是(1)表征在打桩冲击载荷下的土桩响应,以及(2)了解如何根据LRFD将生成的信息用于改善承受垂直载荷的桩的设计和施工控制。已经理解的是,如果桩阻力随时间的增加(即桩的建立)可以量化并纳入LRFD中,则可以提高桩基础的效率。由于当前的桩基础实践在设计和验证桩性能方面涉及不同的方法,因此,桩性能的差异通常会导致桩规格的调整,从而导致建筑成本增加,施工延误以及其他相关的调度问题。尽管本研究的重点是最先进的动态分析方法,例如打桩分析仪(PDA),波动方程分析程序(WEAP)和CAse桩波浪分析程序(CAPWAP),但是这些方法在估计和验证桩性能方面的准确性在很大程度上取决于动态土壤参数的输入选择,这些参数尚未根据测得的土壤性质成功进行量化。为了克服这些问题,并且由于爱荷华州历史数据库(PILOT)提供的数据有限,十个满量程字段在爱荷华州对钢制H桩(HP 250 x 63)进行了测试。在测试桩附近完成了使用标准渗透率测试(SPT)和锥形渗透率测试(CPT)进行的详细的原位土壤调查。安装了推入式压力传感器,以测量在测试桩使用寿命期间的总侧向土压力和孔隙水压力。进行了土壤表征和固结测试。使用PDA监控驾驶过程中,驾驶结束(EOD)和重震时的桩响应。 PDA记录用于CAPWAP分析中以评估桩的性能。此外,还记录了锤击次数以进行WEAP分析。在完成所有的限制之后,进行静载荷测试以测量桩的阻力。;从测试中收集的信息提供了桩设置的定性和定量研究。与文献中的经验性桩设置方法不同,根据土的固结系数,SPT N值和桩半径建立了解析半经验方程,以系统地量化桩设置。这些建议的方程式不需要进行桩架冲击或载荷测试;两者都是耗时且昂贵的。这些拟议方程的成功验证为估计嵌入粘性土壤中的H型钢桩的设置提供了信心和准确性。对于大位移桩的类似研究,结果表明,所提出的方法为较小直径的桩提供了更好的桩身预测。;基于对可用数据库进行的统计评估,现场测试以及文献中的资料,确定在EOD处的初始桩阻力和桩桩阻力的估计中存在不同的不确定性。为了解决此差异,通过扩展一阶第二矩(FOSM)方法,同时保持相同的目标可靠性水平,建立了将桩设置合并到LRFD中的过程。研究结果提供了一种基于任何区域数据库确定EOD和设置阻力的阻力因子的方法。因此,现在可以将桩设置的实际实施包括在桩设计中,而最新的美国国家公路和运输官员协会(AASHTO)桥梁设计规范中并未提供该桩设计。将PILOT数据库与现场测试结果相结合为了建立动力分析方法,建立了在粘土,沙子和混合土剖面中嵌入的桥梁深层基础的区域校准阻力因子。与最新的AASHTO桥梁设计规范所建议的相比,这种局部校准产生了更高的阻力系数并提高了桩性能。此外,使用动态分析方法的这些校准结果作为施工控制方法,通过开发施工控制程序,增强了用作设计方法的爱荷华州内部方法(爱荷华州蓝皮书)的阻力因子。考虑到施工控制因素,可最大程度地减少设计和桩身阻力之间的差异,并将施工控制方法纳入设计过程的一部分。改进了CAPWAP信号匹配程序,可更好地量化动态土阻尼系数和地震值,沿竖井和桩脚的不同土壤特性。相关性研究导致开发了几个经验方程,这些方程可使用测得的SPT N值来量化动态土壤参数。此外,结果揭示了桩的设置和桩的安装对动态土壤参数的影响。通过改善CAPWAP信号匹配质量,验证了这些估算的动态土壤参数的应用。

著录项

  • 作者

    Ng, Kam Weng.;

  • 作者单位

    Iowa State University.;

  • 授予单位 Iowa State University.;
  • 学科 Geotechnology.;Engineering Civil.
  • 学位 Ph.D.
  • 年度 2011
  • 页码 316 p.
  • 总页数 316
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类
  • 关键词

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号