首页> 外文会议>World Organization of Dredging Associations(WODA) World Dredging Congress; 20070527-0601; Lake Buena Vista,FL(US) >TARGETED DREDGING OF NEAR-SHORE DEBRIS AND SEDIMENT, UPPER TRENTON CHANNEL, DETROIT RIVER: A CASE STUDY
【24h】

TARGETED DREDGING OF NEAR-SHORE DEBRIS AND SEDIMENT, UPPER TRENTON CHANNEL, DETROIT RIVER: A CASE STUDY

机译:近岸碎屑和沉积物,特伦顿河上游,底特律河的定向疏D:案例研究

获取原文
获取原文并翻译 | 示例

摘要

Under regulatory orders, dredging was conducted to remove up to 30.000 cubic yards (cy) (22,900 m~3) of contaminated sediments and debris along approximately 1,200 ft (366 m) of the west shoreline of the Upper Trenton Channel, Detroit River in Riverview Michigan. The objective was removal of overlying materials to the surface of a regional clay layer prior to installation of a sheet pile groundwater barrier along the shoreline for closure of an historical upland waste disposal area. Water depths ranged up to 27 ft (8.2 m) and current velocities up to 2.4 feet per second (0.73 meters per second [m/s]). The project is presented as a case study with focus on project definition to satisfy regulatory requirements, design and performance of the turbidity control system, equipment selection and performance in debris and fine-grained materials, the contractors' approaches to satisfying performance-based specifications, dredged material handling, and review of project completion metrics.This project area experiences periodic high river velocities, a major design issue for turbidity controls. This design challenge was met using a sheet pile flow deflection wall coupled with a single heavy fabric silt curtain with piling and cable support, and overlapping sections. Velocity measurements and hydrodynamic modeling were used for design, to test alternative configurations and potential impacts to an adjacent bridge pier. A dual criteria turbidity action level was requested in the permit and compliance monitoring utilized telemetric data collection, visual time-trend monitoring and alarm notification of exceedences. Dredging employed shore-based long reach excavators and barge mounted cranes operating clam shells and a Cable Ann environmental clamshell. During dredging, shoreline bank slopes were field-modified from design for stability and the sheet pile wall installation immediately followed dredging. Dredging was performed in fall 2006 and contingency planning had to consider potential for freeze-out.Debris separation from sediments was a regulatory requirement. Debris had significant impacts on production rates and equipment durability. Field modification to dredge cut reporting was implemented to deal with repeat damage to position sensors in removing large debris. In meeting these challenges, dredging was completed in the November 2006 - January 2007 period. This presentation will be a useful case study review to future projects conducted in similar settings and with similar requirements.
机译:根据监管命令,在河景城底特律河上特伦顿河道西海岸线约1,200英尺(366 m)处进行挖泥,清除多达30.000立方码(cy)(22,900 m〜3)受污染的沉积物和碎屑。密西根州目的是在沿海岸线安装板桩式地下水屏障以封闭历史性高地废物处置区之前,先将覆盖材料清除到区域性粘土层的表面。水深达27英尺(8.2 m),流速达每秒2.4英尺(0.73米/秒[m / s])。该项目是一个案例研究,重点关注项目定义,以满足法规要求,浊度控制系统的设计和性能,碎屑和细颗粒物料的设备选择和性能,承包商满足基于性能的规范的方法,疏material物料处理,并审查项目完成指标。该项目区域会经历周期性的高河流速度,这是浊度控制的主要设计问题。通过使用板桩流动偏转墙以及带有打桩和电缆支撑以及重叠部分的单个重型织物淤泥幕墙,可以解决此设计难题。速度测量和流体动力学建模用于设计,以测试替代配置和对相邻桥墩的潜在影响。在许可证中要求采用双重标准的浊度操作水平,并通过遥测数据收集,可视化的时间趋势监视和超出警报通知合规性监视。挖泥采用岸基长距离挖掘机,以及安装蛤壳和Cable Ann环境蛤壳的驳船吊车。在疏ed过程中,对海岸线的岸坡进行了从设计到现场的修改,以确保稳定性,并在疏followed之后立即安装板桩墙。疏ed工作于2006年秋季进行,应急计划必须考虑潜在的冻结现象。从沉积物中分离碎屑是一项法规要求。碎片对生产率和设备耐用性有重大影响。对挖泥机报告进行了现场修改,以解决在清除大碎屑时对位置传感器造成的重复损坏。为应对这些挑战,疏2006工作已于2006年11月至2007年1月完成。此演示文稿将是有用的案例研究回顾,可用于在类似环境和类似要求下进行的未来项目。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号