Method Study of Software Project Schedule Estimation Guide

机译:软件项目进度估算指南的方法研究

获取原文

摘要

To ensure the estimation accuracy of software project schedule and improve the timely completion of the projects, a quantitative estimation guide of software project was studied combined with some actual project cases. A non-linear regression curve was obtained by the use of statistical analysis methods, on base of this a schedule estimation guide model was built and the use of the model was studied. By the significant test of this model, we found that the regression effect is not significant. That means the schedule is not only affected by the effort, but also by many other factors, this function can only be used to verify the reasonableness of the estimated results of the schedule, and could not be used to be a direct basis for schedule arrangement. The actual data shows that this model could provide help for the schedule estimation, and could improve the schedule estimation accuracy.
机译:为了保证软件项目进度表的估计准确性,提高项目的及时完成性,结合实际工程案例,对软件项目的定量估计指导进行了研究。利用统计分析方法获得了非线性回归曲线,在此基础上建立了进度估算指导模型,并研究了该模型的应用。通过对该模型的显着检验,我们发现回归效果不显着。这意味着进度表不仅受到工作量的影响,还受到许多其他因素的影响,此功能只能用于验证进度表估计结果的合理性,而不能用作进度表安排的直接基础。 。实际数据表明,该模型可以为进度表估计提供帮助,并可以提高进度表估计的准确性。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号