In the spring of 2004, the third and final phase of thernCapital Replacement Project (CRP) at the PinellasrnCounty Resource Recovery Facility (PCRRF) wasrncompleted. Construction work was on schedule andrnwithin budget. The primary effort of the CRP was thernredesign, demolition and reconstruction of the threern1,050 TPD boilers from the top of the furnace (1st pass)rnthrough the economizer outlet (4th pass). This paperrnreviews the rebuild of the boilers along with therncorresponding improvements in municipal solid wastern(MSW) throughput and electrical generation via twornturbine generator (T/G) sets.
机译:2004年春季,Pinellasrn县资源回收设施(PCRRF)的“资本替代计划”(CRP)的第三阶段也是最后阶段已经完成。施工工作如期进行,预算内。 CRP的主要工作是从炉顶(第一遍)到省煤器出口(第四遍)对三台1,050 TPD锅炉进行重新设计,拆除和重建。本文回顾了锅炉的改造以及相应的市政固体废物(MSW)产量和通过两台涡轮发电机(T / G)进行发电的改进。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号