The Montana Tunnels Mine was mined out to arndepth of 900 feet at the end of 1999. The first signsrnof instability were recognized in 1996 along thernupper slope area of the northwest sector when thernpit was mined out to a depth of approximately 500rnfeet. To extend the life of mining operations, it hasrnbeen proposed to extend and steepen the northwestrnhighwall to a depth of 1000 feet. Slope stabilityrnanalyses were carried out using the UDEC softwarernprogram to assess the stability and deformation ofrnthe proposed highwall design. Back analysis of anrninstability in 1997 along the upper slope section andrnhighwall deformation to date has indicatedrnreasonable agreement with the observed mode ofrnfailure and displacement monitoring results. Thernresults of detailed analyses of the proposed highwallrndesign have indicated very limited additionalrndeformation, further development of tension cracksrnis unlikely and large-scale instability is not expectedrnto occur. A total of 40% of additional mining hasrnbeen completed and ongoing displacementrnmonitoring to date has confirmed very limitedrnadditional movement and no further tension crackrndevelopment.
机译:Montana隧道矿在1999年底被开采到900英尺的深度。1996年,在西北部的rnupper坡度地区开采了大约500rnfeet的深度时,首次发现了岩浆不稳定性。为了延长采矿作业的寿命,已经提议将西北高墙延长并加深到1000英尺的深度。使用UDEC软件程序进行了边坡稳定性分析,以评估所建议的高墙设计的稳定性和变形。对1997年沿上坡部分的不稳定和迄今为止的高墙变形的反分析表明,与观察到的破坏和位移监测结果的模式具有合理的一致性。对拟议的高墙设计进行详细分析的结果表明,附加变形非常有限,张力裂缝的进一步发展不太可能,并且预计不会出现大规模的不稳定性。总共有40%的额外采矿工作已经完成,到目前为止,对流离失所情况的监测已证实额外的活动非常有限,并且没有进一步的张力裂缝发展。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号