RIVERSIDE BADLANDS TUNNEL, INLAND FEEDER PROJECT: THE CHALLENGES BETWEEN CONCEPT AND COMPLETION

机译:内弗德河河道巴德兰兹隧道:概念和完成之间的挑战

获取原文

摘要

The Riverside Badlands Tunnel is a 13 km (8 mile) long segment of the Inland Feeder Project. This 3.65 m (12 ft) finished diameter water tunnel presented many challenges that had to be overcome to take the project from concept to reality, not the least of which were the diverse ground conditions. Construction of the tunnel was carried out by a single tunnel boring machine (TBM) in one tunnel drive. The project is considered a success due to the accurate baseline established for the ground conditions; the approaches used to mitigate adverse conditions; and the appropriate use of TBM excavation methods, which achieved rapid advance rates despite the challenging ground conditions.
机译:Riverside Badlands隧道是内陆支线项目的13公里(8英里)长。这条直径为3.65 m(12 ft)的完工水隧道带来了许多挑战,这些挑战使该项目从概念变为现实,尤其是多样化的地面条件。隧道的建设是在一个隧道驱动器中由一台隧道掘进机(TBM)进行的。由于为地面条件确定了准确的基准,因此该项目被认为是成功的;减轻不利条件的方法;以及适当使用TBM开挖方法,尽管地面条件艰苦,但掘进速度很快。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号