首页> 外文会议>Rapid Excavation and Tunneling Conference >WOLF CREEK UPPER NARROWS PROJECT-SOUTH FORK, COLORADO, CONSTRUCTION OF A LARGE CROSS-SECTION DRILL AND BLAST HIGHWAY TUNNEL IN ALPINE CONDITIONS WITH MULTIPLE STAGGERED HEADINGS
【24h】

WOLF CREEK UPPER NARROWS PROJECT-SOUTH FORK, COLORADO, CONSTRUCTION OF A LARGE CROSS-SECTION DRILL AND BLAST HIGHWAY TUNNEL IN ALPINE CONDITIONS WITH MULTIPLE STAGGERED HEADINGS

机译:狼C上颚项目-南叉,科罗拉多州,大型横断面钻头和爆破公路隧道,多头井斜施工

获取原文
获取外文期刊封面目录资料

摘要

This paper discusses the overall challenges to construct a two-lane highway tunnel located in southwestern Colorado on U.S. Highway 160 for the Colorado Department of Transportation by the Kiewit Western Company. The purpose of this project is to provide the excavation and temporary support for a highway tunnel 280 m (916 feet) long. The tunnel cross section is 14.3 m (47 feet) wide by 8.5 m (28 feet) high, 105 m~2 (1, 130 SF). Construction methods include conventional drill and blast excavation with rockbolt and shotcrete ground support. This unique tunnel is being constructed under alpine tunnelling conditions and in the immediate vicinity of active highway traffic.
机译:本文讨论了由Kiewit Western Company在科罗拉多州西南部的160号公路上为科罗拉多州交通运输部建造一条两车道高速公路隧道的总体挑战。该项目的目的是为一条长280 m(916英尺)的公路隧道提供挖掘和临时支撑。隧道横截面宽14.3 m(47英尺),高8.5 m(28英尺),高105 m〜2(1,130 SF)。施工方法包括常规的钻探和爆破开挖以及锚杆和喷射混凝土地面支撑。这条独特的隧道是在高山隧道条件下以及在繁忙的公路交通附近建造的。

著录项

获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号