首页> 外文会议>Proceedings of the Western Dredging Association Twenty-Eighth Technical Conference and Thirty-Ninth Texas Aamp;M Dredging Seminar >INTRODUCTION OF THE NEW USEPA AND USACE INTEGRATED SAMPLINGAND ANALYSIS PLAN/QUALITY ASSURANCE PROJECT PLAN (SAP/QAPP) TO ASSIST IN THE PRE-DREDGING ASSESSMENT AND PERMITTING PROCESS
【24h】

INTRODUCTION OF THE NEW USEPA AND USACE INTEGRATED SAMPLINGAND ANALYSIS PLAN/QUALITY ASSURANCE PROJECT PLAN (SAP/QAPP) TO ASSIST IN THE PRE-DREDGING ASSESSMENT AND PERMITTING PROCESS

机译:引入新的USEPA和USACE集成采样和分析计划/质量保证项目计划(SAP / QAPP),以协助进行预挖矿评估和许可过程

获取原文
获取原文并翻译 | 示例

摘要

The current procedure for pre-dredging assessment and dredge material disposal permitting begins with the preparation of a Scope of Work (SOW) and/or Sampling and Analysis Plan (SAP) prepared by the client or permit applicant and a Quality Assurance Project Plan (QAPP) prepared by the sampling contractor. The SAP is intended to provide all the necessary information about a project and allow the sampling contractor to prepare the QAPP, which explains how the work will be accomplished and how all applicable requirements, e.g. Data Quality Objectives (DQOs), Target Detection Limits (TDLs), collecting samples within the dredge prism, etc., will be met. These documents, however, have no fixed formats and are often submitted with incomplete or incorrect information, causing possible delays in the overall schedule. This paper will discuss how the U.S. Environmental Protection Agency Region 4 (EPA Region 4) and several U.S. Army Corps of Engineers (USACE) districts have jointly adopted a set of protocols, combining the two documents into one and establishing a new template (Integrated SAP/QAPP) to be used for all dredged material ocean disposal projects in the southeastern United States. The new format is expected to streamline the process by generating a single comprehensive document and will eventually be incorporated into the national guidance for dredged material management. The new template was developed to be used by all permit applicants in conjunction with federal, state, and private projects. The template was recently tested in a pilot project before being released to applicants. Implementation of the new model revealed that it could easily be adapted for use in areas where environmental concerns arise due to non-standardized procedures. The Integrated SAP/QAPP incorporates easy-to-follow instructions within the document, allows for multiple authors within one document, enables integration of sections at different stages of the project, and provides a completed example to further assist the applicant in addressing relevant environmental concerns in the final document.
机译:当前的挖泥前评估和挖泥机材料许可的程序始于准备由客户或许可申请人准备的工作范围(SOW)和/或抽样和分析计划(SAP)以及质量保证项目计划(QAPP) )由采样承包商准备。 SAP的目的是提供有关项目的所有必要信息,并允许采样承包商准备QAPP,该文件说明了如何完成工作以及如何满足所有适用要求,例如:将满足数据质量目标(DQO),目标检测极限(TDL),在挖泥棱镜内收集样本等。但是,这些文档没有固定的格式,并且经常以不完整或不正确的信息提交,从而可能导致整个进度表的延迟。本文将讨论美国环境保护局第4区(EPA第4区)和美国陆军工程兵团(USACE)几个地区如何共同采用一套协议,将两个文件合并为一个协议并建立新模板(集成SAP / QAPP)将用于美国东南部的所有疏material材料海洋处置项目。预计新格式将通过生成一个综合性文件来简化流程,并将最终纳入疏dr材料管理的国家指南中。开发了新模板,供所有许可证申请人与联邦,州和私人项目一起使用。该模板最近在一个试点项目中进行了测试,然后再发布给申请人。新模型的实施表明,可以很容易地将其适应于因非标准化程序而引起环境问题的地区。集成的SAP / QAPP在文档中合并了易于遵循的说明,在一个文档中允许多位作者,在项目的不同阶段集成了各个部分,并提供了一个完整的示例来进一步帮助申请人解决相关的环境问题在最终文件中。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号