The improvement on the construction science and technique in the daxia hydropower station in the yellow river

机译:黄河大峡水电站施工科学技术的改进。

获取原文
获取原文并翻译 | 示例

摘要

The Daxia Hydropower Station lies in Beiying County of Ganshu Province which belongs to the upstream district of the Yellow River. During the course of its construction, the factor which limits the high construction speed is many problems about design and construction. In the construction practice, in order to quicken the pace of main works and ensure the construction quality, we optimized the scheme of design and construction, worked out rational construction measure. We modified the scheme of overlapping placements in power house, abolished closed blocks in draft tube of power house, changed the turf cofferdam of tertiary foundation pit to stop-log gate, used the new technique on connection of steel bars and the conditioning water for roughening concrete surface widely, and so on. As a result of these measures, the height of dam concrete in hydropower station in river channel was increased 60m in a year, the first unit began to generate power half a year ahead of time.
机译:大峡水电站位于甘肃省北营县,属黄河上游地区。在其施工过程中,限制高施工速度的因素是设计和施工中的许多问题。在施工实践中,为加快主体工程进度,确保施工质量,我们优化了设计施工方案,制定了合理的施工措施。修改了厂房重叠布置方案,取消了厂房引水管封闭块,将第三基坑草皮围堰改为挡木闸,采用了新的钢筋与调节水连接技术进行粗化混凝土表面广泛等等。由于采取了这些措施,河道水电站大坝混凝土的高度一年增加了60m,第一台机组提前半年开始发电。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号