P-07 Design and Fabrication of the Reactor Vessel Cooling System (VCS) in HTTR

机译:P-07 HTTR中反应堆容器冷却系统(VCS)的设计和制造

获取原文
获取原文并翻译 | 示例

摘要

The reactor Vessel Cooling System (VCS) is one of the engineered safety features used as a residual heat removal system when forced circulation in both the primary and auxiliary cooling systems cannot be performed simultaneously. The VCS consists of a Cooling Water Panel (CWP) and a water circulation system supplying a coolant. The CWP is installed on the surface of the concrete wall of the Reactor Pressure Vessel (RPV) room to remove heat from the RPV by thermal radiation. The water circulation system is installed in the reactor building and transfers heat, removed by CWP to a cooling tower.rnIn view of the limited temperatures of the RPV and fuel at the loss-of-coolant accident, it is necessary to design a VCS in accordance with stipulated requirements, limited heat removal values and limited temperature of the concrete. We will describe the Design and Fabrication of the water circulation system, especially for the CWP in the present paper giving conclusive evidence to support the results which met the stipulated requirements.rnFabrication of the VCS-panel was completed and the VCS-panel was installed into the RPV room last year. The piping systems of VCS are flushed and a pressure test for the system will be performed shortly. A component test of the circulation pumps for the VCS will be carried out in March, this year. Heat removal values will be measured to confirm the results of analysis along with collecting field data for the start up test in 1998.
机译:当主冷却系统和辅助冷却系统中的强制循环不能同时执行时,反应堆容器冷却系统(VCS)是用作余热排除系统的工程安全功能之一。 VCS由冷却水面板(CWP)和供应冷却液的水循环系统组成。 CWP安装在反应堆压力容器(RPV)室混凝土墙的表面上,以通过热辐射从RPV去除热量。水循环系统安装在反应堆建筑物中,并通过CWP转移热量至冷却塔。rn鉴于冷却液损失事故中RPV和燃料的温度有限,有必要在VCC中设计VCS。根据规定的要求,有限的散热值和有限的混凝土温度。我们将在本文中描述水循环系统的设计和制造,特别是对于CWP,这将提供确凿的证据来支持符合规定要求的结果。-完成了VCS面板的制造,并将VCS面板安装到去年的RPV室。 VCS的管道系统已冲洗,不久将对该系统进行压力测试。用于VCS的循环泵的组件测试将于今年3月进行。将测量除热值,以确认分析结果,并收集现场数据,以进行1998年的启动测试。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号