A gold mine, located in the Middle East, required a modification to its existing tailing storage facility to (1) reduce seepage losses from the existing unlined facility, (2) capture water being lost to seepage for use in a new heap leach operation, and (3) increase capacity. A unique aspect of this project was the founding of the 15-meter-high, HDPE-lined containment over 40 percent of the existing unlined facility. The tailing deposited in the existing facility served as the foundation for the modification and provided a smooth surface for the subsequent geosynthetic liner on both the basin and upstream embankment slopes. Sub-aerial deposition was used as the method of placing the tailing, creating a drained deposit for environmental stewardship, increased capacity, and ease of reclamation. The modified facility has been in operation since 1995. The design, construction, commissioning, and reclamation aspects of the tailing facility modification are discussed.
机译:位于中东的一处金矿需要对其现有的尾矿存储设施进行改造,以(1)减少现有的无衬砌设施的渗漏损失,(2)收集流失的渗漏水以用于新的堆浸操作, (3)增加容量。该项目的一个独特方面是建立了15米高,HDPE衬里的容器,占现有未衬设备的40%以上。沉积在现有设施中的尾矿用作改建的基础,并为盆地和上游路堤斜坡上的后续土工合成衬砌提供了光滑的表面。地下沉积被用作放置尾矿的方法,为环境管理,增加容量和简化填海创造了排水的沉积物。改造后的设施自1995年开始投入运营。讨论了尾矿设施改造的设计,建造,调试和开垦方面。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号