3-D Simulating Analysis for Thermal Control during Construction Period on Dahuashui RCC Arch Dam

机译:大华水碾压混凝土拱坝施工期热力控制的三维模拟分析

获取原文
获取原文并翻译 | 示例

摘要

The Dahuashui dam is the highest RCC arch dam with the height of 134. 5m. Including the factors of creep, accumulated self-weight and cool pipes, 3-D simulating analysis were carried out from the construction to operation according to the measured data and the actual construction process. The results show that the cracks occurred during the early construction period is mainly caused by thermal stress. The dam would be safe during the periods of the first winter and impoundment by insulating the upstream and downstream faces of the dam.
机译:大华水坝是最高的碾压混凝土拱坝,高134. 5m。包括蠕变因素,累积的自重和冷却管在内,根据实测数据和实际施工过程,对从施工到运营的3D模拟分析。结果表明,施工初期产生的裂缝主要是由于热应力引起的。通过隔离大坝的上游和下游面,在第一个冬季和蓄水期间,大坝将是安全的。

著录项

  • 来源
  • 会议地点 Guiyang(CN)
  • 作者

    Tao Li; rnWei Mao;

  • 作者单位

    Li Penghui@Department of Hydraulic Engineering, Tsinghua University, Beijing 100084, China--Chen Hong@Guiyang Hydropower Investigation, Design Research Institute, China Hydropower Engineering Consulting CO., GuiZhou 550002, China--Luo Hongbo@Guiyang Hydropower Investigation, Design Research Institute, China Hydropower Engineering Consulting CO., GuiZhou 550002, China--Hu Yu@Department of Hydraulic Engineering, Tsinghua University, Beijing 100084, China--Jin Feng@Department of Hydraulic Engineering, Tsinghua University, Beijing 100084, China--;

  • 会议组织
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类 挡水坝;
  • 关键词

    RCC arch dam; thermal stress; crack; cooling pipe;