Assessment of Soil Setup from Pile Installation Monitoring and Restrike Tests of Offshore Wind Turbine Foundation Piles

机译:海上风机基桩桩身安装监测与回弹试验的土体设置评价

获取原文
获取外文期刊封面目录资料

摘要

According to German recommendations for offshore wind turbine foundations, the bearing capacity of axially loaded piles can be verified by dynamic load testing. However, during the pile-driving process, the soil resistances are reduced, requiring additional setup time to increase again. This setup effect has been discussed in several presentations, e.g., at stress wave conferences. The resistance obtained from signal-matching analysis procedures (e.g., CAPWAP~?) are thus a function of the elapsed setup time. In many cases, the static resistance to driving observed at the end of initial driving does not provide adequate capacity, even at final penetration. Thus, restrike tests after a sufficient waiting time after pile installation are typically required to determine the long-term resistance. Especially under the harsh ambient conditions at offshore sites, the performance of restrike tests is a challenge, and many actions and procedures must be considered to obtain reliable capacity results and setup factors.
机译:根据德国对海上风力涡轮机基础的建议,轴向荷载桩的承载力可通过动荷载试验进行验证。然而,在打桩过程中,土壤阻力降低,需要额外的设置时间才能再次增加。这种设置效应已在多个演示中讨论过,例如在应力波会议上。通过信号匹配分析程序(例如CAPWAP~?)获得的电阻因此,是经过的设置时间的函数。在许多情况下,在初始行驶结束时观察到的静态行驶阻力无法提供足够的通行能力,即使是在最终穿透时。因此,通常需要在桩安装后等待足够的时间后进行重燃试验,以确定长期阻力。尤其是在海上现场的恶劣环境条件下,重燃试验的性能是一个挑战,必须考虑许多措施和程序,以获得可靠的容量结果和设置系数。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号