Excavation and monitoring of the main tailrace tunnels of the Xiangjiaba underground power station

机译:湘家坝地下发电站主尾隧道的开挖和监控

获取原文

摘要

The main tailrace tunnel of the Xiangjiaba right bank underground power station has the biggest designed cross-section dimension of its kind in the world. Due to this fact, its construction is complex. The principle of "top arch" lining first, then "excavation down" was adopted based on the location conditions during construction and thus addressed the issue of super-big cross-section tunneling works. The safety monitoring data of the project indicate that the stress strain develops in line with the project development law and demonstrate that the parameters designed for the excavation and support are reasonable. Construction safety meets the design requirements and the tunnel remains safe and stable. Therefore, the method for this tailrace tunnel can be used as a reference for other similar projects.
机译:Xiangjiaba右岸地下电站的主要尾隧道具有最大的设计横断面维度。由于这一事实,其建筑很复杂。 “顶拱”衬里原则首先是基于施工期间的位置条件采用“挖掘下来”,从而解决了超大横截面隧道作品的问题。该项目的安全监测数据表明,压力应变与项目开发法发展符合,并证明为挖掘和支持设计的参数是合理的。施工安全符合设计要求,隧道保持安全稳定。因此,该尾部隧道的方法可以用作其他类似项目的参考。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号