The existing optimized operation of circulating water system does not suit piping-main scheme circulating water system with double-pressure condenser. The optimum vacuum of piping-main scheme should be defined as the vacuum which makes the difference between the sum of the two units' added electric power and the circulating water pump power maximum. The plan of optimized operation of piping-main scheme circulating water system which is based on this kind of optimum vacuum was put forward. And a specific example of 2×660MW units was given, the power plant's optimized operation mode of the whole circulating water system at difference conditions was obtained. The results show that the optimized scheme is correct and suit the piping-main scheme circulating water system, and the optimized operation can well improve the steam turbine economy.
机译:循环水系统的现有优化操作不适合带双压冷凝器的管道主方案循环水系统。配管主方案的最佳真空应定义为真空,这使得两个单位增加的电力和循环水泵功率最大值之间的差异。提出了基于这种最佳真空的管道主题方案循环水系统的优化操作计划。给出了2×660mW单位的具体例子,获得了在差状条件下整个循环水系统的发电厂的优化操作模式。结果表明,优化方案是正确的,适合管道主方案循环水系统,优化的操作可以完善汽轮机经济。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号