首页> 外文会议>CIGRE ZAGREB Symposium on Transient Phenomena in Large Electric Power Systems >Some peculiarities in insulation coordination and mitigation measures against extreme sea salt pollution on Croatian 110 kV 'Islands connection'
【24h】

Some peculiarities in insulation coordination and mitigation measures against extreme sea salt pollution on Croatian 110 kV 'Islands connection'

机译:对克罗地亚110千伏“群岛联系”对极端海盐污染的绝缘协调和缓解措施的一些特殊性

获取原文

摘要

Among Croatian transmission lines (rated voltages of 110 kV, 220 kV and 400 kV) one combined 110 kV line (OHL + submarine cables) is particularly interesting due to its characteristics and environmental influences to which it is exposed. It is s.c. "110 kV Islands Connection" (see Fig. 1), a combination of overhead lines and submarine cables between great towns Rijeka and Zadar on Adriatic coast passing over great islands Krk, Rab and Pag (with one branch over islands Cres and Losinj) in total length of about 170 km (including about 30 km of 4 sections of submarine cable). There are four 110 kV "passing or tapped type" substations on islands (RP Omisalj, TS Rab, TS Pag and TS Nin), two "meshed type" substations (TS Krk and TS Novalja) - all in AIS version - and eight 110 kV s.c. "cable houses" or "cubicles" (transitions: submarine cable - OHL) with 110 kV bushings. High voltage equipment - particularly outdoor insulators - in open space and even in "cable houses" are exposed to extreme sea salt pollution from the nearby Adriatic Sea.
机译:在克罗地亚传输线中(110 kV,220 kV和400 kV的额定电压),一个110 kV线(Ohl +潜艇电缆)由于其特征和环境影响而特别有趣。这是s.c. “110 kV岛连接”(参见图1),架空线和潜艇电缆的组合,在伟大的岛屿Krk,Rab和Pag的亚得里亚海沿岸的亚得里亚海岸和扎达尔之间的组合(在岛屿Cres和Losinj)中总长度约170公里(包括约30公里的潜艇电缆)。岛上有四个110 kV“通过或敲击型”变电站(RP omisalj,Ts Rab,Ts Pag和Ts nin),两个“网格型”变电站(TS Krk和Ts Novalja) - 全部在AIS版本 - 和8个110 kv sc. “电缆屋”或“级别”(过渡:潜艇电缆 - OHL),具有110 kV衬套。高压设备 - 特别是户外绝缘体 - 在开放空间,即使在“缆绳房”中也暴露于附近亚得里亚海的极端海盐污染。

著录项

相似文献

  • 外文文献
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号