首页> 外文会议>North American tuneling : conference and exhibition >Instrumentation controls for chemical grouting during tunneling operations. Boston, Massachusetts
【24h】

Instrumentation controls for chemical grouting during tunneling operations. Boston, Massachusetts

机译:隧道运算过程中化学灌浆的仪表控制。波士顿,马萨诸塞州

获取原文

摘要

The Central Artery Tunnel Project located in Boston Massachusetts is the largest and most complex highway project in American history. One of the Projects main elements is the replacement of the elevated Interstate 93 through downtown Boston with an underground highway. At its deepest point the underground highway is 120 feet (36 meters) below grade and passes directly beneath an existing subway tunnel/station. To tunnel beneath the existing subway a significant underpinning structure was required consisting of stacked drift tunnels and post tensioned roof girders or cross adits. To facilitate mining two shafts were dropped approximately 120 feet (36 meters), the water table was temporarily lowered and two access tunnels/grouting galleries were mined in a cohesive granular till. The underlying stacked tunnel drives were driven in pervious gravel deposits overlaying Argillite bedrock. The stacked tunnel drives and cross adits were mined open face with a combination of ribs and liner plates. Permanent dewatering could not be performed due to settlement concerns, since, the nearby adjacent high rises bear on mat foundations and the nearby historical structures are supported on timber pile foundations bearing in clay. To facilitate the open face mining, of the lower drifts in the pervious gravel soils, ground stabilization was required. Prior to the ground modification being performed, an instrumentation system was installed and initialized in the active transit tunnel located approximately 1 meter (3 feet) above the crown of the access tunnels. The instrumentation system included 3 separate "strings" of vibrating wire liquid level displacement transducers. The strings, each approximately 50 meters (150 feet) long, were installed along the inbound and outbound track platforms and along the cen-terline columns between the tracks. All of the strings were connected to an Automated Data Acquisition System (ADAS) which was monitored remotely via modem. Ground modification was performed by injecting sodium silicate grout through tube-a-manchette or TAM pipes creating a mass of chemically stabilized soil under each access tunnel. During the early grouting program vertical upward deformations were measured by the liquid level system and confirmed by optical survey. Multiple modifications were made in an attempt to limit the heave while still creating the required grout curtains. Such modifications included: additional pressure relief via dewatering wells, reductions in injection pressures, reductions in flow rates, reductions in the grout viscosity, revisions to the grouting sequence, reductions in the number of active packers, a replacement of sodium silicate with acrylate grout. All of the contract modifications were performed under a heave based limiting criteria. In summary, the monitoring system provided a degree of confidence during the grouting operations allowing the maximum amount of grout to be injected while maintaining heave within acceptable limits to the Owner. Over 950,000 liters (250,000 gallons) of grout were injected and the drifts and cross adits have been successfully mined without incident.
机译:位于波士顿马萨诸塞州的中央动脉隧道项目是美国历史上最大,最复杂的公路项目。其中一个项目主要元素是用地下高速公路更换电梯93到波士顿市中心。在最深的点处,地下高速公路低于等级低120英尺(36米),直接通过现有地铁隧道/站。在现有地铁下方的隧道中,需要大量的底层结构,包括堆叠的漂移隧道和张紧的屋顶梁或交叉配套。为了便于采矿两轴落下约120英尺(36米),水位暂时降低,两次接入隧道/灌浆画廊在粘性粒度下开采。底层堆叠的隧道驱动器被驱动为覆盖泥石石基岩的可透过砾石沉积物。堆叠的隧道驱动器和交叉配套采用肋骨和衬垫板的组合开孔。由于沉降问题,无法进行永久脱水,因为,附近的附近高升高率在席位和附近的历史结构上都是支持粘土中的木材桩基础的支持。为了促进开放的面部挖掘,在透水砾石土中的较低漂移,需要地面稳定性。在进行地面修改之前,安装仪器系统并在位于接入隧道的冠部上方约1米(3英尺)的有源传输隧道中。仪表系统包括3个振动线液位位移换能器的单独的“串”。每个大约50米(150英尺)长,沿着入站和出站轨道平台安装串,沿着轨道之间的CEN-TERLINE列安装。所有字符串都连接到自动数据采集系统(ADA),通过调制解调器远程监视。通过将硅酸钠灌浆喷射通过管 - A-曼皮或TAM管来进行地面改性,在每个进入隧道下产生大量的化学稳定的土壤。在早期的灌浆期间,通过液位系统测量垂直向上变形,并通过光学测量证实。尝试进行多种修改,以限制升降,同时仍然产生所需的灌浆窗帘。这些修改包括:通过脱水井的额外压力消除,注射压力的减少,流速减少,灌浆粘度的减少,灌浆序列的修订,减少活性封装机的数量,用丙烯酸盐填充硅酸钠的替代钠。所有合同修改都是在基于吊索的限制标准下进行的。总之,监测系统在灌浆操作期间提供了一定程度的置信度,允许注入最大灌浆量,同时保持对所有者的可接受限度的升压。注入超过950,000升(250,000加仑)的灌浆,并在没有事件的情况下成功开采了漂移和交叉配合。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号