首页> 外文会议>International Mechanical Engineering Congress and Exposition >EXERGOECONOMIC ANALYSIS IN A CEMENT PRODUCTION PLANT
【24h】

EXERGOECONOMIC ANALYSIS IN A CEMENT PRODUCTION PLANT

机译:水泥生产厂的Exergo经济分析

获取原文

摘要

A dry-type Cement Production Plan of 151 Tons per hour was taken as a case of study to implement an exergoeconomic analysis. In this paper, the exergy destruction and the investment costs of the system's units were calculated to obtain accurate information about the performance of the process, from the exergoeconomic factor and the relative difference cost. Conventional exergoeconomic analysis showed that the total cost of exergy destruction is 4206537 USD/h. The Calciner and the Rotary Kiln cause 62% of the total cost of the exergy destruction. The lowest values of the exergoeconomic factor were calculated for Calciner (0.01%), Clinker Cooler (0.01%), Rotary Kiln (0.02%), and Raw Mill (0.04%). The significant difference in relative cost was calculated for Calciner (42%) and Rotary Kiln (54.21%). The above implies that this equipment should be considered for an investment that allows the decrease of the exergy destruction cost and the increase of the exergetic efficiency.
机译:将每小时151吨的干式水泥生产计划作为实施exergo经济分析的案例。 在本文中,计算了系统单位的毁灭和投资成本,以获得关于该过程性能的准确信息,从Exergo经济因素和相对差异成本。 常规的Exergo经济分析表明,漏洞破坏的总成本为4206537美元/小时。 煅烧窑和旋转窑导致漏洞破坏总成本的62%。 计算Exergo经济因素的最低值,计算煅烧炉(0.01%),熟料冷却器(0.01%),旋转窑(0.02%)和原厂(0.04%)。 对煅烧炉(42%)和回转窑(54.21%)计算相对成本的显着差异。 以上意味着应该考虑该设备的投资,以降低漏洞的破坏成本和促进效率的增加。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号