Results of the return air raise silencer system upgrade at Totten Mine

机译:托特矿井返回空气升级消音系统升级

获取原文

摘要

The Totten Mine project specified two parallel main return air fans located on-surface eguipped with baffle silencers designed to attenuate the sound levels from the fan outlets. In late 2014, an acoustical study determined that the return air fans were responsible for a series of noise disturbances in a community situated approximately 9 km to the northeast. The results of the acoustical study also indicated that the silencers were significantly underperforming due to clogging with a combination of particulate and moisture drawn from the underground mine. During 2015 and the beginning of 2016, Totten Mine implemented a cleaning procedure to mitigate the underperformance of the silencers. Unfortunately, noise monitoring of the cleaning procedures indicated diminishing results over time. As a result, a temporary solution was identified and implemented in Q3 and Q4 of 2016 to allow adequate time for engineering and defining of a long-term solution. The proposed temporary solution, however, had the potential to become the permanent solution, subject to an evaluation of performance. This paper presents the results of the temporary solution evaluation, when compared to the baseline cleaning procedure. The temporary solution is then compared to the proposed alternatives thqt were to be part of a feasibility study for both capital (CAPEX) and operational (OPEX) cost evaluation. The resulting long-term solution to manage noise issues on mine return air systems, similar to the Totten experience, is also presented and discussed.
机译:托特矿山项目指定了两个平行的主返回空气风扇,位于表面上,例如挡板消音器,旨在衰减风扇出口的声级。 2014年底,一项声学研究确定,返回空气粉丝负责距离东北大约9公里的社区中的一系列噪声障碍。声学研究的结果还表明,由于从地下矿的颗粒和水分的组合堵塞,消沉剂显着表现得显着。 2015年和2016年初,托特矿井实施了清洁程序,以减轻消音器的表现。不幸的是,清洁程序的噪声监测表明随着时间的推移结果递减。结果,在2016年的Q3和Q4中识别并实施了临时解决方案,以允许适当的工程时间和定义长期解决方案。然而,拟议的临时解决方案有可能成为常可解决方案,但须评估性能。与基线清洁程序相比,本文提出了临时解决方案评估的结果。然后将临时解决方案与拟议的替代品进行比较,该替代方案是资本(CAPEX)和运营(OPEX)成本评估的可行性研究的一部分。由此产生的长期解决方案,用于管理矿山返回空气系统上的噪声问题,类似于托特的经验,并讨论并讨论。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号