STEP-FEED BNR PROCESS ACHIEVING TN < 4 mg/LA Case Study of WSSC-Piscataway WWTP, Prince George's County, Maryland

机译:步骤饲料BNR过程实现TN <4 Mg / LA案例研究WSSC-PISCATAWAY WWTP,马里兰州乔治郡王子

获取原文

摘要

Piscataway WWTP is a 30 MGD advanced plant with average flow of 18 MGD, operating 3 of 4 parallel basins (see attached plant schematic). It is operated by Washington Suburban Sanitary Commission (WSSC), and located in Prince George's County, Maryland. The Plant undertook one of the first large-scale Step-Feed BNR applications in the nation, which went on line in the fall of 2000 with the purpose of achieving a seasonal goal of 8 mg/l TN. The step-feed process was selected due to its lower construction cost compared with other BNR processes, yet meeting the State's program to get POTW's to voluntarily meet a seasonal TN goal of 8 mg/l. The lower construction cost is attributed to smaller basins, no internal recirculation pumps, and no methanol addition systems when compared with other more conventional BNR processes. The process was designed to meet a seasonal TN limit of 5 mg/l. During the first year of operation, a monthly trial was conducted on the process, varying one or more operating parameter to test the process. Based on the first year's results, the 2002 operating parameters were adjusted to maximize nitrogen reduction, achieving TN monthly averages less than 4 mg/L from June to November 2002. The retrofit converted two activated sludge processes (Secondary Activated Sludge Process and Nitrification Activated Sludge Process) that were in series into two parallel trains of Step-feed BNR process. Raw wastewater is screened and degritted before Primary clarification. The Primary Effluent is step fed into the BNR basins. Each train is comprised of two identical basins, however the two trains differ significantly from each other: Train 1 basins are 2.65 MG each and comprised of 5 passes each, while Train 2 basins are 2.76 MG each and comprised of 4 passes each. The following table summarizes the characteristics of the basins.
机译:PISCATAWAY WWTP是30 MGD高级工厂,平均流量为18 MGD,操作3的4个平行盆地(见附图厂原理图)。它由华盛顿郊区卫生委员会(WSSC)负责,位于马里兰州乔治王子县。该工厂在2000年秋季进行了第一批大型步进饲料BNR应用中的一个大规模的步骤饲料BNR应用,目的是实现8毫克/吨TN的季节性目标。由于其较低的建筑成本与其他BNR流程相比,逐步选择了步进进料过程,但符合国家计划以获得Potw的季节性TN目标为8毫克/升。较低的施工成本归因于较小的盆地,没有内部再循环泵,并且与其他更常规的BNR工艺相比,没有内部再循环泵,没有甲醇添加系统。该过程旨在满足5mg / L的季节性TN限制。在运作的第一年期间,在流程上进行每月试验,改变一个或多个操作参数来测试该过程。根据第一年的结果,调整2002年的操作参数以最大限度地减少氮气减少,从6月到2002年6月,达到4毫克/升的TN每月平均值。改造转化了两种活性污泥工艺(二次活性污泥工艺和硝化活性污泥过程)串联成两次平行列车的步进饲料BNR过程。在初步澄清之前,筛选并缩短了原料废水。将初级流出物送入BNR盆地。每列火车由两个相同的盆地组成,然而,两个列车彼此显着差异:火车1个盆分别为2.65毫克,每个盆地均由每个盆地均为2.65mg,每个列盆都有5次,每次组成5次,而火车2个盆地每个盆地每次2.76毫克,每次组成。下表总结了盆地的特征。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号