The New Mississippi River Bridge (MRB) employed conventional design-bid-build procurement, but the bidding process included the opportunity for pre-qualified bidders to develop and propose confidential Alternative Technical Concepts (ATC's) for evaluation and approval in advance of bidding. The ATC process provides a mechanism for value-engineering prior to bid, with incentives and opportunities for both the owner and the bidding contractor. The contract described in this paper is for the river bridge composed of a cable-stayed crossing with two pylons and the anchor piers on each side of the river. The Massman-Traylor-Alberici (MTA) team developed a redesigned foundation system for the main pylon and anchor foundations which utilizes their equipment and experience along with field load test measurements to optimize the foundations. The paper describes the experience with the use of the pre-bid ATC process on the project from the perspective of the bidder, and outlines some of the benefits and limitations of this concept with respect to foundation design and construction. Some keys for success are identified and impediments to the effective implementation of the process are described.
机译:新的密西西比河大桥(MRB)就业,竞标制剂采购,但竞标过程包括预先合格投标人的机会,以便在投标前进行评估和批准的机密替代技术概念(ATC)。 ATC流程提供了在投标之前的价值工程机制,并为所有者和招标承包商提供激励和机会。本文描述的合同是为河桥组成,由河流停留的横跨两个塔架和河流两侧的锚墩。 Massman-Traylor-Alberici(MTA)团队为主塔和锚基基础开发了一个重新设计的基础系统,锚固基础利用其设备和经验以及现场负荷测试测量来优化基础。本文介绍了在投标人的角度来看,在项目上使用预先出价ATC进程的经验,并概述了这一概念关于基础设计和施工的一些好处和局限性。已经确定了一些成功的键,并描述了对该过程的有效实施的障碍。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号